BPCS/LX Tip of the Day: Accounts Payable / Purchasing

Anthony Etzel 0 981 Article rating: No rating

You can integrate Accounts Payable (ACP) with Purchasing. ACP requires more detailed information in the Vendor file than Purchasing requires. Accounts Payable automatically checks for a valid purchase order when you

match invoices to POs and receipts. Enter any outstanding active purchase orders through PO Release, PUR500, before you can match invoices in Accounts Payable.

 

Accounts Payable can also update the Actual Cost fields in the Inventory Master file directly from vendor invoices. You must provide the following information in order for Accounts Payable to complete this update:

â–ª Define a type C inventory transaction.

â–ª Enter a valid purchase order on the Invoice Entry header screen, ACP500D2-01, or in the Next Purchase Order field on the Invoice Entry: PO Costing screen, ACP500D3-01.

â–ª Enter the information for the actual cost transaction on the appropriate lines.

Baan/LN Tip of the Day: Virtualization

Kathy Barthelt 0 46437 Article rating: No rating

The advantages of virtualization include the following:
 

• You get more out of your existing resources. Pool common infrastructure resources and break the legacy “one application to one server” model with server consolidation.

• You can reduce datacenter costs by reducing your physical infrastructure and improving your server to admin ratio. Fewer servers and related IT hardware means reduced real estate and reduced power and cooling requirements. With better management tools, you can improve your server to admin ratio so personnel requirements are reduced.

• You can increase the availability of hardware and applications for improved business continuity.

• Securely back up and migrate entire virtual environments with no service interruptions. Eliminate planned downtime and recover immediately from unplanned issues.

• Gain operational flexibility. Respond to market changes with dynamic resource management, faster server provisioning, and improved application deployment.

 

The disadvantages of virtualization include the following:

 Virtualization adds overhead to the CPU, memory, IO, and network.

 Virtualization adds an additional layer to the hardware and software stack. Therefore, additional complexity is introduced in the following circumstances:

CST Industries Goes Live With LN Ecommerce Site for Dealers

Crossroads RMC 0 29848 Article rating: No rating

Crossroads RMC has partnered with Xenitel Managed Service Solutions and CST Industries to create an online parts ordering site for CST’s dealers. The site is live as of June, 2015. This site was developed largely to simplify the ordering process for CST’s dealers, providing information on available inventory, flexible ordering, fast shipments, and improved dealer support.

 

CST is a global leader in the manufacture and construction of factory coated metal storage tanks, aluminum domes and specialty covers.

Baan/LN Tip of the Day: First Free Numbers

Kathy Barthelt 0 316 Article rating: No rating

In Baan IV, users define series and numbers in the Maintain First Free Numbers (tcmcs0147m000) session. In the Type of Number field, users must select the type of documents for which the series will be used. The generated document numbers are always numeric and can consist of up to six characters.

 

In LN, users must define number groups in the Number Groups (tcmcs0151m000) session and then in the First Free Numbers (tcmcs0150m000) session, define the series and numbers of each number group. Users assign the number groups to various purposes in the corresponding sessions. For example, in the Sales Order Parameters (tdsls0100s400) session, users can select the number group for sales orders and sales schedules. In the Sales Offices (tdsls0512m000) session, users can then select a series of that number group for the sales orders generated by a specific sales office. As the series codes can be alphanumeric, the generated document numbers can be alphanumeric and they can consist of up to nine characters.

BPCS/LX Tip of the Day: Material Requirement Dates and Lead Time Offsets in MRP

Anthony Etzel 0 343 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Week: Database Sizing – Moving to LN

Kathy Barthelt 0 219 Article rating: No rating
The Infor LN database must be created with the appropriate size. For example, if at least 150 GB is required for a year, create the database with the required size from the beginning. Do not let the size increase to the required size and cause additional fragmentation in the database and the NTFS volume.  Set the autogrowth to a minimum of 10 percent or 1 GB (for each extent) to avoid fragmentation on file system level. Never use the default extent size of 1 MB.

How Do You Measure Success in Your Business?

Anthony Etzel 0 52554 Article rating: 5.0

Business owners may measure success in different ways – some tangible, some intangible.

In order to establish how you should measure success for your business, you need to first examine how you measure your personal success. If you are a business owner, or a part of the management team of the company you work for, ask yourself these questions to see how you measure up:

Assess personal success.

1.    Am I happy in my job?

2.    Do I have passion for what I’m doing?

3.    Do I get the desired results based on the effort I’m putting in?

4.    Am I putting forth my best effort?

5.    Am I patient and allow for sufficient time to see results?

6.    Do I get respect from my co-workers?

7.    Do I have the endurance to hang in there when things get a bit rough?


Reflect on successes and failures.

After answering these questions, do you need to make any changes? Do you still have the same ambition and drive to achieve the goal? Are you content with your work, or have you come to the conclusion that you have not done your best?

To be successful...

First109110111112114116117118Last

Tips:  LX | BPCS | M3

Anthony Etzel
/ Categories: Infor LX & BPCS Tips

BPCS/LX Tip of the Week: Shop Order Status

You can see the status of the Shop Order when using SFC300 Shop Order Inquiry. You want to be sure that your shop orders are at the correct status in order to report against them.

The following are the shop order status codes:

04 = The Shop order has been entered.

05 = The Shop order has been released and printed.

14 = The Shop order has been released, but not printed. If a shop order is at this status, you have released it and it is not printed due to a system failure, or the order has been put on hold.

XX = The Shop order is closed.

Previous Article BPCS/LX Tip of the Week: Work Center & Machine Locations
Next Article BPCS/LX Tip of the Week: Indirect Labor Reporting
Print
73590 Rate this article:
No rating

Contact

Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

x

Tips: LN | Baan

To create a purchase order (with subcontracting) third party outsourcing from purchase order, execute these steps:

  1. Create a purchase order using the same data set defined in the Subcontracting Models (tisub1100m000) session.
  2. In the Purchase Order Intake Workbench (tdpur4601m200) session, click New. The Purchase Order (tdpur4100m900) session is displayed.
  3. ...