BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 62452 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 58246 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

BPCS/LX Tip of the Week: Receiving to Inspection

Anthony Etzel 0 66168 Article rating: No rating

If the item being received needs to be inspected prior to being available for use, there are two schools of thought.

The first is to receive the item to a QC hold location. The downside is the item will show up in on hand inventory.

A better method would be to do a PO receipt to inspection. Both Inv500 and Pur550 support this method. Now you have received the item without showing it in inventory. Only the PO quantity in inspection is updated. This method also allows you to create an Inspection Dispatch Report. After the QC process for the item is complete, then the transaction Receipt from Inspection to Stock is processed. That transaction then updates the PO quantity received field and the Item on hand field in inventory.

Baan/LN Tip of the Week: Purchase Inquiry

Kathy Barthelt 0 84282 Article rating: No rating

In Baan IV Purchase Control, the purchase inquiry procedure enables the user to:

  • Request a specific supplier to submit a quotation on the purchase inquiry for the delivery of an item.
  • Compare the prices and discounts of the quotations that are submitted by different suppliers.
  • Copy the inquiry data to a purchase order.


In LN, you can:

  • Request multiple business partners to submit a quotation on a specific request-for-quotation for the delivery of an item.
  • Compare the received quotations based on the following criteria:
  1. Price
  2. Quantity
  3. Vendor rating
  4. Delivery dates
  5. RFQ subjective criteria
  • Copy the quotation data to a purchase order, a purchase contract, or a price book.

BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 58338 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 59712 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

Filtec Selects Crossroads RMC for Baan Data Collection

Kathy Barthelt 0 28831 Article rating: No rating

Filtec, a leading provider of in-line inspection solutions for the food, beverage, and pharmaceutical industries, has selected the Web Collect, formerly RMC3 data collection solution from Crossroads RMC for their Baan IV system. Filtec plans to implement Labor Reporting and Report Operations Complete as part of this project with the goal of eliminating manual data entry and gaining better visibility to gap time. The project is scheduled to go live in early November 2015.

BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

Anthony Etzel 0 63362 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

First108109110111113115116117Last

Tips:  LX | BPCS | M3

New IDF Inquiries 

Infor LX has a long history of providing IDF inquiries over most critical business areas, but there are still some areas that lack this capability.
The following IDF inquiries are now available in 8.4.2:

  • Customer Quote
  • Customer Quote Line
  • RMA (Return Material Authorization)
  • RMA Line

Benefits

  • Ability to sort, subset, filter, and view information in a modern and intuitive way
  • Point and click navigation to related information – 360 views
    • Exceptional personalization and extensibility capabilities

New IDF Inquiries 

Infor LX has a long history of providing IDF inquiries over most critical business areas, but there are still some areas that lack this capability.
The following IDF inquiries are now available in 8.4.2:

  • Customer Quote
  • Customer Quote Line
  • RMA (Return Material Authorization)
  • RMA Line

Benefits

  • Ability to sort, subset, filter, and view information in a modern and intuitive way
  • Point and click navigation to related information – 360 views
    • Exceptional personalization and extensibility capabilities
Last

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for EXECUTIVES

FINANCE Tip: Remap Posted Integration Transactions (tfgld4282m100)

Use this session to remap Posted transactions that were mapped incorrectly.

To remap integration transactions successfully, several conditions must be fulfilled. For details, refer to To remap integration transactions.

Enter the ranges of selection criteria for the integration transaction or range of integration transactions to be remapped. You can select the integration transactions of a range of business objects or of a specific business object.

You must select a specific integration document type or an integration document type group.

To evaluate the remapping before you perform the actual remapping, you can select the Simulate check box and the Error Report check box. After you solve the errors, you can run the session again and clear the Simulate check box.

After remapping the integration transactions, you can use the Post Integration Transactions (tfgld4282m000) session to create the postings in the General Ledger.

OPERATIONS Tip: Using Country of Origin for Purchase Orders

For purchase orders, information about the COO allows you to track the related import duties, tariffs, and compliance with sourcing requirements. You can maintain the COO of an item when creating an order or the release level of a purchase order.

When you create a purchase order line in the Purchase Order Lines (tdpur4101m000) session, the COO related details are defaulted based on the item-purchase data defined in the Items - Purchase (tdipu0101m000) session. To view this data, you can use the Country of Origin option from the References menu in the Purchase Order Lines (tdpur4101m000) session.

After the order line is released to Warehousing, an inbound line is created in the Inbound Order Lines (whinh2110m000) session with the COO information. A receipt line is created in the Warehouse Receipt Lines (whinh3512m100) session when the inbound order line is received. To view the actual COO for the item specified on the receipt line, you can use the Country of Origin option from the References menu in this session.

You can view the country of origin (COO) data for the inventory received in a warehouse in the Item - Country of Origin Inventory (tcitu6600m000) session based on the data specified in the header section such as, warehouse, item, and so on.

In the Inventory Tracking Receipt (tcitu2610m000) session, you can view the information related to the purchase order, inventory quantity, and actual COO of the item. You can use the Intrastat Transactions (tccom7171m000) session to view the COO that is reported for an order line and is used for the Intrastat declaration.

TECHNOLOGY Tip: Impact of Configuration Changes on Audit Trails:

Impact of Configuration Changes on Audit Trails

The impact of changes in the audit settings varies depending on the specific circumstances. The issues typically arise when changes made to audit settings are implemented at runtime without requiring all users to exit the system (LN). As a result, some users may continue to generate audit trails using the old configuration, while those who log in after the changes take effect will create audit trails based on the new configuration.

Changes in User Profiles

Below is a summary table that illustrates the effects of these changes for a specific table within a company:

Change Description Impact
Add a table Users that still use the old settings do not audit some transactions.
Remove a table Some transactions that must not be audited with the new settings are still audited by users that use the old settings.
Change the audit type for a table or field Some transactions are audited according to the old settings, and other transactions are audited according to the new settings.
Add or remove a field After you audit transactions in the table with the new settings, users that use the old settings can no longer perform transactions on this table. Therefore, users with the old settings can be forced to restart LN.

Note on Changes in Field-Specific Auditing:
When you toggle field-specific auditing on or off for a table, which alters the number of fields being audited, the effect is analogous to adding or removing a field. However, not every modification to the audit settings impacts the runtime settings. Converting the new settings to runtime might result in no net change for the entire configuration if the overall effect of the adjustments neutralizes each other.

Previous Article Infor LN & Baan Tips & Tricks for TECHNOLOGY: Impact of Configuration Changes on Audit Trails
Next Article Infor LN & Baan Tips & Tricks for EXECUTIVES
Print
37103 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories