Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 58215 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

BPCS/LX Tip of the Week: Receiving to Inspection

Anthony Etzel 0 66117 Article rating: No rating

If the item being received needs to be inspected prior to being available for use, there are two schools of thought.

The first is to receive the item to a QC hold location. The downside is the item will show up in on hand inventory.

A better method would be to do a PO receipt to inspection. Both Inv500 and Pur550 support this method. Now you have received the item without showing it in inventory. Only the PO quantity in inspection is updated. This method also allows you to create an Inspection Dispatch Report. After the QC process for the item is complete, then the transaction Receipt from Inspection to Stock is processed. That transaction then updates the PO quantity received field and the Item on hand field in inventory.

Baan/LN Tip of the Week: Purchase Inquiry

Kathy Barthelt 0 84272 Article rating: No rating

In Baan IV Purchase Control, the purchase inquiry procedure enables the user to:

  • Request a specific supplier to submit a quotation on the purchase inquiry for the delivery of an item.
  • Compare the prices and discounts of the quotations that are submitted by different suppliers.
  • Copy the inquiry data to a purchase order.


In LN, you can:

  • Request multiple business partners to submit a quotation on a specific request-for-quotation for the delivery of an item.
  • Compare the received quotations based on the following criteria:
  1. Price
  2. Quantity
  3. Vendor rating
  4. Delivery dates
  5. RFQ subjective criteria
  • Copy the quotation data to a purchase order, a purchase contract, or a price book.

BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 58320 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 59690 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

Filtec Selects Crossroads RMC for Baan Data Collection

Kathy Barthelt 0 28820 Article rating: No rating

Filtec, a leading provider of in-line inspection solutions for the food, beverage, and pharmaceutical industries, has selected the Web Collect, formerly RMC3 data collection solution from Crossroads RMC for their Baan IV system. Filtec plans to implement Labor Reporting and Report Operations Complete as part of this project with the goal of eliminating manual data entry and gaining better visibility to gap time. The project is scheduled to go live in early November 2015.

BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

Anthony Etzel 0 63304 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Week: Data Sizing Moving to LN

Kathy Barthelt 0 57435 Article rating: No rating

The Infor LN database must be created with the appropriate size. For example, if at least 150 GB is required for a year, create the database with the required size from the beginning. Do not let the size increase to the required size and cause additional fragmentation in the database and the NTFS volume.  Set the autogrowth to a minimum of 10 percent or 1 GB (for each extent) to avoid fragmentation on file system level. Never use the default extent size of 1 MB.

First108109110111113115116117Last

Tips:  LX | BPCS | M3

New IDF Inquiries 

Infor LX has a long history of providing IDF inquiries over most critical business areas, but there are still some areas that lack this capability.
The following IDF inquiries are now available in 8.4.2:

  • Customer Quote
  • Customer Quote Line
  • RMA (Return Material Authorization)
  • RMA Line

Benefits

  • Ability to sort, subset, filter, and view information in a modern and intuitive way
  • Point and click navigation to related information – 360 views
    • Exceptional personalization and extensibility capabilities

New IDF Inquiries 

Infor LX has a long history of providing IDF inquiries over most critical business areas, but there are still some areas that lack this capability.
The following IDF inquiries are now available in 8.4.2:

  • Customer Quote
  • Customer Quote Line
  • RMA (Return Material Authorization)
  • RMA Line

Benefits

  • Ability to sort, subset, filter, and view information in a modern and intuitive way
  • Point and click navigation to related information – 360 views
    • Exceptional personalization and extensibility capabilities
Last

Tips: LN | Baan

Crossroads RMC

Finance: How much time are you wasting on manual processes?

Time-consuming processes around month-end close, year-end close, AP matching, invoicing, account reconciliation, vendor payments, tax compliance, and more can weigh down a Finance team. Your business and your customers’ needs have changed and you are in a constant battle to keep up. It's hard to know which area to tackle first and where the greatest impact can be made.

That's where the Crossroads RMC Finance Utilization Review comes in.
Whether you're on an old version of BPCS or Baan, or the latest version of Infor LX or Infor LN, odds are there are aspects of Finance in the ERP system that doesn't fit your business's current strategy. Do you throw out the software and start with something new? Odds are that is overkill. Sometimes it just boils down to taking the time to understand how your current state matches up with your corporate strategy, understanding the gaps, and developing a plan to get you from point A to point B.

We have successfully helped companies transform their business in the areas of:

  • Procure to Pay
  • Record to Report
  • Quote to Cash
  • Financial Planning & Analysis

Our Finance consultants have 30+ years of experience that bring about REAL change. We work at your pace and in a way that makes the most sense to your business. Our consultants can review current usage and related business processes of your entire ERP system, or a particular area like Finance, and make recommendations that will reinvigorate your ERP system and those that use it.

A utilization review can be performed 100% remotely via phone or web meeting, or in person, following safety guidelines.

Get started > with a FREE 1-hour phone assessment to determine if your business can benefit from a Finance Utilization review!

Sources: Hackett Group & McKinsey.com

Print
31748 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

x

Categories