Anthony Etzel 0 54257 Article rating: 5.0

Understanding: How many hours remain in total and at each operation?

First let’s look at some key BPCS Master File data starting with the routing file.

How many routing steps (operations) are set up that reflect how the product is produced in the factory? If you take a short cut and set up only one operation for the entire process, then you will limit the information seen on the SO inquiry program. Set up the operation steps to reflect what you want to report back to from the factory floor.

Will each of the routing steps run in one work center, or in different work centers? To keep it simple you may want to set up work centers as departments. For example:

  • Assembly
  • Machine
  • Paint
  • Etc.

For each operation setup consider how you have set up the following:

  • Load Codes – for example a code 5 is used if reporting both setup time and run labor time. These codes are maintained in the work center file
  • Basis Code – typical codes are P for pieces per hour,  3 is used for hours per 1,000 pieces
  • Setup hours – if you set them up, you also want to report them
  • Run hours – Direct Labor
  • Machine hours

How you set up th

Baan/LN Tip of the Week: ERP Setup - Pros & Cons

Kathy Barthelt 0 56158 Article rating: No rating

You may have started your setup of your ERP system one way, and have discovered over time that maybe it no longer fits how you need to do business. Over the next few weeks, I’ll be providing some pros/cons to consider for different company setups.

Pros/Cons of Single Finance / Single Logistic Company Set-Up

Pros
Easy to implement and to maintain.
No risk of processing data for another company.
Data not visible across companies – pro if you do not want users to see other company’s data.
Cost Prices can be different for the same item in the different logistics companies.
Easy to add or remove companies when companies are bought or sold.
Accounting functions are all separate by company. – Pro if each finance company is managed separately.
 

 

Cons
Decentralized operations – purchasing, sales, manufacturing, planning, warehousing, etc.
User must go in and out of companies if there is a need to view or create transactions in more than one company.

It’s NOT All About the Money, Money, Money… Motivating Employees in the New Year!

Kathy Barthelt 0 37269 Article rating: 5.0

Have you ever thought about what really motivates your employees?

It’s not about the almighty dollar, you know. Ok, ok…..money doesn’t hurt, but money alone doesn’t keep most people in their jobs. You actually need to motivate your employees to keep them showing up, mentally, and physically. Employees that don’t feel motivated are probably underperforming, and that means you’re losing money.

Ask yourself these questions about your employees:

  • Are they happy…..YES….HAPPY! Do they enjoy coming to work every day?
  • Do they feel challenged, or do they feel demeaned?
  • Are they sinking, or are they swimming?
  • Do they have the right tools in their arsenal to battle the giants?
  • Where’s the reward?

Happiness - I’ve worked with manufacturers for almost 20 years now...

BPCS/LX Tip of the Week: Financial Year End – Have you done all you need to do?

Anthony Etzel 0 55623 Article rating: No rating

Came across an article online from Lauber CFO’s, and thought I would share. Here is a checklist for things to consider in order to finish out the year and help you plan for 2016:

 

  • Are your accounting records up to date so that you can make a projection of how the current year will turn out?
  • Are all account reconciliations currently up to date to facilitate the closing of the books after year end?
  • Are there accounts receivable that should be reserved for or written off prior to the end of the year?
  • If your business carries inventory, do you need to plan a physical count as of the end of the year?
  • Has depreciation on your fixed assets been recorded during the year? Have you considered depreciation on current year additions?
  • Have all new asset purchases and bank loans been recorded on your books?
  • Are there any liabilities, for example, pending legal actions or warranty issues, which will need to be recorded prior to year end? 
  • Do you have a plan in place to properly “cut-off” revenue at year end to properly match revenue and expense?
  • Will there be bonuses, profit sharing contributions or discretionary retirement plan contributions paid prior to the end of the year? How will these payments affect cash f

Baan/LN Tip of the Week: Financial Year End – Have you done all you need to do?

Kathy Barthelt 0 50001 Article rating: No rating

Came across an article online from Lauber CFO’s, and thought I would share. Here is a checklist for things to consider in order to finish out the year and help you plan for 2016:

  • Is your accounting records up to date so that you can make a projection of how the current year will turn out?
  • Are all account reconciliations currently up to date to facilitate the closing of the books after year-end?
  • Are there accounts receivable that should be reserved for or written off prior to the end of the year?
  • If your business carries inventory, do you need to plan a physical count as of the end of the year?
  • Has depreciation on your fixed assets been recorded during the year? Have you considered depreciation on current year additions?
  • Have all new asset purchases and bank loans been recorded on your books?
  • Are there any liabilities, for example, pending legal actions or warranty issues, which will need to be recorded prior to the year-end? 
  • Do you have a plan in place to properly “cut-off” revenue at year-end to properly match revenue and expense?
  • Will there be bonuses, profit sharing contributions, or discretionary retirement plan contributions paid prior to the end of the year? How will these payments affect cash flow?
  • Will you be in compliance with your bank covenants at year-end?
  • Do you need to make arrangements to receive statements as of the end of the year for the cash value of life insurance, loan balances, etc.?

BPCS/LX Tip of the Week: Using Pre-Assigned Lot Numbers

Anthony Etzel 0 50140 Article rating: No rating

Some items in the manufacturing process may require a lot number. A quick and easy way to release the Shop Orders with lot numbers is by using the Multi-Level Shop Order Release.

Simply select the end item from the selection screen and use action 10 for the multi-level order release. At the bottom of the release screen is the field “Pre-Assign a Lot Number to Shop Orders”. Select 1 for the pre-assigned lot number assignment option.

This option will use the pre-assigned lot number on the shop order, if the lot number exists. If the lot number does not exist, the system will automatically create a lot number and assign it to the shop order for all items that are lot-controlled.

CST Adds Warranty Service Claim System to Dealer Portal for LN

Crossroads RMC 0 31862 Article rating: No rating

Crossroads RMC has once again partnered with Xenitel Managed Service Solutions and CST Industries to create a warranty service claim system for CST’s dealers. The project will provide a way for dealers to create a “warranty request claim” from within the dealer portal, defining the customer and product, and parts that failed, and selecting what parts they are claiming for replacement to install the replacement part. This service will be offered in addition to the parts online ordering system previously developed for CST. 

 

CST is a global leader in the manufacture and construction of factory coated metal storage tanks, aluminum domes and specialty covers.

First103104105106108110111112Last

Tips:  LX | BPCS | M3

Item Facility Master has a new attribute to define the override inspection days lead time CICP.ICINSD.

  • When an item facility has a defined override inspection days lead time, that value will be used instead of the system parameter inspection days lead time.

MRP exception report, MRP200B
Purchase planning report, PUR285B
Purchase order / Requisition maintenance, PUR500D3
Purchase order consolidation / release, PUR640B1
Vendor splits, PUR653B

This enhancement improved the subfile utilized in MRP320D Master Schedule Detail Inquiry -SCR001 by expanding the subfile with data rather than clearing the subfile as user pages. This change provides full support for the WebTop 4.8 Grid decorator.

This enhancement updated the approach used to populate the subfile to allow a deployed Webtop Grid to function correctly. There is no visible or user-impacted change to the way the program functions.

This enhancement provides improved functionality and full support of a Webtop grid applied to the subfile.

Last

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for EXECUTIVES

TECHNOLOGY: Data Sharing Methods (Advantages and Disadvantages)

Depending on the multicompany scenario you choose, an implementation team must decide whether or not tables must be logically linked or if data must be synchronized in another way to achieve availability of data across various companies. 

There are 3 ways in which data may be shared among companies. Here are some advantages and disadvantages of each:

  1. Logical Table Linking - If two companies use the same physical data, the physical table exists, or is used, in only one company: the physical company. Each piece occurs only once: one instance of the same data. If the term logical table linking is used, users from multiple companies use a single physical instance of the data. If the company tables are on the same server, this can be accomplished by logical table linking. Access to specific data can be restricted, if required.

    • Advantages: Logical Table Linking takes place in real time; therefore, the moment a record is created or modified in one company, a record becomes available in all other linked companies as well. The setup and maintenance of logical table linking is easier than the setup and maintenance of data replication. Logical table linking is extremely reliable because this type of linking is independent of network connections and user interventions. 

    • Disadvantages: Table sharing implies that all attributes for a record are the same in all companies. Therefore, suppose you share the item table and, for a particular item in a company, the product class is XXX. In this case, in all other companies, the product class for this item must be XXX as well.

  2. Data Replication - In this situation, each company has exactly the same data, but each company has a unique copy of the data. The same piece of data exists in multiple (physical) places: multiple instances of the same data. The process to copy the data is called data replication.

    • Advantages: Rather than using table sharing by means of the logical linking of tables, you can replicate the content of tables between companies. The advantage is that, on company level, some (non-key) attributes of a record can differ by company. For example, if the bills of materials are replicated instead of shared, for each company, you can link a different warehouse to the bill of material. As a result, the bills of materials can be the same across all companies and only the warehouses differ. Using replication, you can also make only a subset of the records available in other companies. For example, if you replicate items between companies, in a sales company, for example, by means of the item group, you can only make end items available. In addition, you can replicate only a subset of items, for example, depending on the item group. Note that replication also requires that the referenced tables are replicated or shared.

    • Disadvantages: Replication is not in real time, and therefore, for processes that require real-time integrated data as the financial integration processes, replication is not an option. For replication, you also must take into account the sequence in which you replicate. First, you must replicate the child tables and then the parent tables, and therefore first the business partners and then the purchase contracts. During the replication process, the data must be frozen. This point is of particular importance if the replication process takes a lot of time.

  3. Manual Syncronization - If only a small number of records are the same between some companies, you can enter, maintain, and keep the records synchronized manually. Note that the more dynamic data is, the more difficult this process is. This solution is strictly procedural. Therefore, depending on the discipline of the users, the solution is error sensitive: data can be forgotten, updated too late, or typing errors may occur.

  • Advantages - The main advantage is the flexibility so that only the data that really must be shared can be kept synchronized. By manually keeping data synchronized, not all attributes of a record need to have the same value.

  • Disadvantages - The main disadvantage is that this method depends on user interaction. Therefore, the method depends on the user’s time - because the method is not a real time procedure and the user may forget to update the data - and users can make mistakes.

OPERATIONS: Creating a Purchase Order with Subcontracting

To create a purchase order (with subcontracting) third party outsourcing from purchase order, execute these steps:

  1. Create a purchase order using the same data set defined in the Subcontracting Models (tisub1100m000) session.
  2. In the Purchase Order Intake Workbench (tdpur4601m200) session, click New. The Purchase Order (tdpur4100m900) session is displayed.
  3. Select the business partner in the Business Partner field, Press Tab. Note: Infor LN populates the default data for the selected business partner in the other fields of the purchase order header.
  4. Select the order type for subcontracting in the Order Type field, purchase office in the Purchase Office field, and the related order series in the Order field.
  5. Click New on the Order Lines tab and select your subcontracted price item in the second segment of the Item field.
  6. Specify the required quantity in the Ordered Quantity field, price of the item in the Price field and click Save.
  7. Click the Approve button to approve the purchase order. The purchase order Status is updated to Approved.
  8. Verify that the material to be sent to the subcontractor is updated on the Material Supply Lines tab.
  9. Select the material line on the Material Supply Lines tab and click Actions > Generate Supply Order.
  10. Select the generated supply order line updated in the Supply Order Line field on the Material Supply Lines tab and click References > Supply Lines. The Warehousing Order (whinh2100m100) session is displayed.
  11. Select the outbound order line on the Outbound Lines tab and click References > Status Overview. The Outbound Line Status Overview (whinh2129m000) session is displayed.
  12. In the Outbound Line Status Overview (whinh2129m000) session, ensure that the Generate Outbound Advice and the Release Outbound Advice activities are automatically executed.
  13. On the specific menu, click Freeze/Confirm. The Shipment Lines (whinh4131m000) session is displayed.
  14. Select the shipment line and click Confirm. The shipment line Status is updated to Confirmed on the Status tab.
  15. Verify that the Line Status is Shipped for the outbound order line on the Outbound Lines tab in the Warehousing Order (whinh2100m100) session.

FINANCE: Cash Flow Statements (tfgld 0123m100)

Use this session to define or maintain cash flow statements and hierarchical structures of cash flow reasons for cash flow statement reports. 

On the Cash Flow Reasons by Statement tab, you can select cash flow reason groups and cash flow reasons to build a hierarchical structure of cash flow reasons for the cash flow statement report.

To link a child cash flow reason group to a parent cash flow reason group:

  1. In the Parent Cash Flow Reason Group field, select the parent cash flow reason group.
  2. In the Child Cash Flow Reason Group field, select the child cash flow reason group.
  3. Leave the Child Cash Flow Reason field empty.

To link a cash flow reason to a cash flow reason group:

  1. in the Parent Cash Flow Reason Group field, select the cash flow reason group
  2. Make the Child Cash Flow Reason Group field empty.
  3. In the Child Cash Flow Reason field, select the cash flow reason.

Note: To link cash flow reasons to a child cash flow reason group, you must select the child cash flow reason group in the Parent Cash Flow Reason Group field.

Previous Article Infor LN & Baan Tips & Tricks for EXECUTIVES
Next Article Infor LN & Baan Tips & Tricks for TECHNOLOGY: Data Sharing Methods (Advantages and Disadvantages)
Print
18654 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories