BPCS/LX Tip of the Week: Changing the Master Schedule

Anthony Etzel 0 47064 Article rating: No rating

You can change your master schedule by specifying the type of master schedule update to perform. You can run a Net Change or Regenerative Schedule.

You also have the ability to clear the lower level requirements out of the Planned and Firm-Planned Order file.

Baan/LN Tip of the Week: ERP Setup - Pros & Cons

Kathy Barthelt 0 71414 Article rating: No rating

Pros
Each legal entity can have its own general ledger and balance sheet.
Income statements can be generated for the different logistics companies.
Accounting user must go in and out of companies if there is a need to view or create transactions in more than one company.  However, if all companies are tied to the same financial group company, centralized payments, cash receipt application, and display and printing of ledger transactions and trial balances are possible for both companies from within the financial group company.

Cons

BPCS/LX Tip of the Week: Understanding What Goes On Out On The Factory Floor – Part 4

Anthony Etzel 0 52818 Article rating: No rating

Understanding: What Was Issued to the Shop Order

The shop order inquiry program provides several function keys. By using the function key for the material, the display will present what components have been issued under the issued quantity column. You are also presented with the required quantity. While viewing the quantities you may see that more was issued than what was required. Possibly there was scrap and more material was required to be issued. Perhaps there was an over issue and the balance of the material is slated to be returned to stock.

A red flag should go up if the Shop Order quantity finished is equal to the required quantity for the end item and all the components have not been issued. You may want to investigate why.

BPCS/LX Tip of the Week: Getting the Most Out of the Shop Order Inquiry Program – Part 3

Anthony Etzel 0 49909 Article rating: No rating

Understanding: The quantities required, finished and remaining at the operation and in total for the Shop Order

The shop order may require 1,000 pieces but only 950 are reported as finished in total for the shop order. The quantity required is what is planned on the SO and it may be a higher number than what is finished, factoring in that there can be scrap. If a 1,000 pieces are required to be produced, and there is always is scrap of 10 pieces, then plan for scheduling a quantity of 1,010.

The quantity finished for the end item is what is reported in the inventory application with a production order receipt transaction. At the operation level, if the quantity is reported at the operation, there will be a value in the PCS Complete field on the operation detail screen showing the pieces completed through that operation.

If you want to get a handle on the difference between the required quantity and the finished quantity, you may want to look into reporting quantities at the operation level as well as examining how scrap is controlled and reported.

Baan/LN Tip of the Week: ERP Setup - Pros & Cons

Kathy Barthelt 0 66781 Article rating: 5.0

Pros/Cons of Multi Finance / Single Logistic Company Set-Up


Pros
Each legal entity can have its own general ledger and balance sheet.
Income statements can be generated for the different enterprise units included in the logistics company.
Centralized operations – purchasing, sales, manufacturing, planning, warehousing, etc.
Logistics data visible to all logistics users – a pro if this is what is desired.
One BOM, Routing, and Cost for each item.

 

BPCS/LX Tip of the Week: Getting the Most Out of the Shop Order Inquiry Program – Part 2

Anthony Etzel 0 57793 Article rating: No rating

Understanding: How many hours remain in total and at each operation?

Now let’s look at what information is being supplied from the shop floor.

It’s not uncommon for transaction reporting to be captured manually on the shop packet that was issued to the factory floor when the SO was released.

The big question is, is anything done with the data? Is it collected and keyed to a  spreadsheet and not shared, or is the transaction data keyed to SFC600? If it is being keyed, ask how often and by whom? Some companies use alternative methods to capture transaction data that do not require batch keying via a keyboard.

Not a lot of data is required to be keyed to SFC600 in order for the SO Inquiry to be useful. The data that should be reported for the transaction process is as follows:

  • The type of hours being reported – machine, run labor, setup labor
  • If reporting setup and run labor you want an employee clock number
  • The shop order and the operation that is being reported
  • Is the operation complete
  • How many good were produced at this operation
  • How many hours – the numbers of hours are critical. Do the employees estimate how many hours they worked, or do they track actual time started and stopped in order to calculate the actual number of hours.

Based on what is captured and how often will have an impact on the SO inquiry screen. Understanding the batch times as to when the transactions are keyed will provide you with the window as to the SO status at that point in time. Or, are they keyed as they happen in a near real time fashion so that you can have a more current view of the factory floor.

Baan/LN Tip of the Week: ERP Setup - Pros & Cons

Kathy Barthelt 0 49920 Article rating: No rating

You may have started your setup of your ERP system one way, and have discovered over time that maybe it no longer fits how you need to do business. Here are some pros/cons to consider for a Single Finance / Multi-Logistic setup. 

 Pros
All accounting functions are centralized into one company.  One balance sheet is generated – even though multiple logistics sites are involved.  Income statements can be generated by logistic company via use of a Dimension to represent the logistic company.

Allows logistical functions to be decentralized within one legal entity – if this is what is desired.

Logistics data not visible across companies – pro if you do not want users to see other company’s data.

 

Cons

Crossroads RMC Maintains Preferred Partner Status With Honeywell / Intermec for 2016

Crossroads RMC 0 32260 Article rating: No rating

Honeywell has renewed Crossroads RMC’s Silver Level status in their Performance Partner Program for 2016. This recognition provides Crossroads RMC with the authorization to resell Honeywell/Intermec mobile computing products at a substantial discount, thereby allowing Crossroads’ customers to take advantage of that discount as well. 

Crossroads works closely with the Honeywell /Intermec engineering group to provide the best hardware offerings at a good price point for manufacturers across North America.

First102103104105107109110111Last

Tips:  LX | BPCS | M3

Item Facility Master has a new attribute to define the override inspection days lead time CICP.ICINSD.

  • When an item facility has a defined override inspection days lead time, that value will be used instead of the system parameter inspection days lead time.

MRP exception report, MRP200B
Purchase planning report, PUR285B
Purchase order / Requisition maintenance, PUR500D3
Purchase order consolidation / release, PUR640B1
Vendor splits, PUR653B

This enhancement improved the subfile utilized in MRP320D Master Schedule Detail Inquiry -SCR001 by expanding the subfile with data rather than clearing the subfile as user pages. This change provides full support for the WebTop 4.8 Grid decorator.

This enhancement updated the approach used to populate the subfile to allow a deployed Webtop Grid to function correctly. There is no visible or user-impacted change to the way the program functions.

This enhancement provides improved functionality and full support of a Webtop grid applied to the subfile.

Last

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

​Infor LN & Baan Tip: Determining What Data to Archive or Delete

Ensuring access to historical logistical and financial transaction information for your employees is crucial. However, before proceeding with archiving or deletion, it's essential to evaluate the necessity of retaining this data. Baan and Infor LN (ERP LN) offer standard archiving sessions within major modules that typically handle a significant volume of historical transactions. These sessions are designed to transfer historical data to an archive company before deleting it from the operational company.

When it comes to archiving sessions, you have three primary options:

  1. Archiving and Deleting: Data is transferred to the archive company and then deleted from the operational company.
  2. Deleting: Data is directly removed from the operational company without archiving.
  3. Archiving Only: Data is moved to the archive company without deletion from the operational company.

It's important to note that options 1 and 2 result in irreversible actions. However, with option 3, where Archiving Only is selected, multiple archiving processes can be executed for previewing results.

Additionally, during archiving sessions, you can typically specify:

  • The cutoff date for the data to be archived.
  • Whether accompanying texts should also be archived.
  • Whether existing texts in the archive company should be replaced.

For more detailed information on archiving procedures, you can refer to the Baan IV and Infor LN documents provided.

Previous Article Infor LN & Baan Tip: Performance improvement by setting the First Free Number Cache (tcmcs0651m000)
Next Article Infor LN & Baan: Customizing Shipping Labels for All Customers
Print
18621 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories