Infor LN & Baan Tip: Navigating the Complexities of Surcharges on Phantom Items in Manufacturing

Is it ok to define surcharges on phantom items?

It is advised not to use surcharges on phantom items for the following reasons:

  1. The usage of phantom surcharges makes it, in general, more difficult to understand, verify, and explain the result of the cost price calculation.
  2. Real phantom items do not exist in real life. It is only an efficient way to specify the BOM. It is therefore questionable if surcharges should be defined for these non-existing phantom items.
  3. The usage of phantom surcharges can lead to variances in production orders, depending on the actual usage of the phantom.
  4. When surcharges based on added costs are defined for both the main item and the phantom item, then the surcharge will be applied twice.

Alternatives are:

  • Define the required surcharges on the main item of the phantom.
  • Define the required surcharges on the sub-item of the phantom.
  • Define a (backflush) operation on the phantom to cover the handling costs (if any) of a phantom item.
Previous Article Infor LX & BPCS Tip: Mastering the Latest Infor LX Innovations for Manufacturing Excellence
Next Article Streamline Your Audit Process: How Crossroads RMC and Avalara Ensure Compliance and Confidence
Print
29647 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

You can change your master schedule by specifying the type of master schedule update to perform. You can run a Net Change or Regenerative Schedule.

You also have the ability to clear the lower level requirements out of the Planned and Firm-Planned Order file.

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

FirstLast

Tips: LN | Baan

Categories