Infor LN & Baan Tips & Tricks for Operations: Copying EBOMs - Which copying method should I use?

To determine which copying method you must use, answer question 1 and follow the instructions.

Question 1: Is the source component a project item (that is, is a project defined in the first segment of the item code)?

  • If the answer is yes, proceed with question 3.
  • If the answer is no, proceed with question 2.


Question 2: Is the target component a project item?

  • If the answer is yes, select copy method NonProj Item to Proj Item.
  • If the answer is no, proceed with question 4.

Question 3: Is there a relationship with the same project?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, proceed with question 4.


Question 4: Is there a relationship with the target item?

  • If the answer is yes, proceed with question 5.
  • If the answer is no, select copy method No Copy Action.


Question 5: Does the item exist already?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, select copy method Copy E-Item to Item.

Previous Article Infor LN & Baan Tips & Tricks for EXECUTIVES:
Next Article Infor LN & Baan Tips & Tricks for Technology: Using audit files in the Exchange module
Print
52615 Rate this article:
5.0

Contact

Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

Use this session to define simulated purchase prices for purchased items per site.

Field Information:

  • Cost Calculation Code - price calculation code
  • Item

The raw materials, subassemblies, finished products, and tools that can be purchased, stored, manufactured, and sold.

An item can also represent a set of items handled as one kit, or which exist in multiple product variants.

You can also define nonphysical items, which are not retained in inventory but can be used to post costs or to invoice services to customers. The examples of nonphysical items:

  • Cost items (for example, electricity)
  • Service items
  • Subcontracting services
  • List items (menus/options)
     
  • ​Site - The site for which the purchase price is simulated.
  • Purchase Currency - The currency of the simulated purchase price.
  • Simulated Price - Purchase price

The simulated purchase price and currency are recorded twice.

  • Simulated Price Multi Currency - The purchase price in multiple currencies.

The simulated purchase price and currency are recorded twice. The amount in this field is related to the price of the supplier.

  • Unit - Purchase price unit
  • Cost Component - The cost component that must be of the type Material Costs.

Note: The cost component specified in this field does not become part of the standard cost detail structure if it is part of the cost component scheme of the selected item. If calculations are performed with a calculation code not used for actualization (simulations only), the simulated purchase price is mapped to the cost component defined in the records for this session.