Infor LN & Baan Tip: Can You Backflush An Item If Estimated Quantity is Zero?

Yes, you can backflush an item with an estimated quantity = 0.00 if you haven't already backflushed the order.

For example, you had an order with one component, you reported the quantity at the operation or order level and ran the backflush. Now you realize you need another component added. In this example, the order has already been backflushed, so if you were to add a second component, run backflushing, nothing would happen.

Backflushing is based on the 'quantity to backflush' in report operations or report orders complete. When the quantity is backflushed, the 'quantity to be backflushed' has been reset to 0.00. With a 0.00 quantity, there is nothing left to backflush so nothing happens. 

In this case, you would have to issue the part through warehousing, just as you would have to do if you had a shortage during the backflushing process. If backflushing hasn't already been attempted, you can backflush a component with zero estimated quantity, after you have reported operations or order complete.

Previous Article Increase Production by 10-20% - It's Simple!
Next Article Infor LX & BPCS Materials Tip: Unique ID Generator / Unique Sequence Number
Print
66446 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).
 

Other options for the field are:


1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.