Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Analytics Dashboard for Infor LN, Baan V and Baan IV

See YOUR data, YOUR way… all without touching your ERP system. 

  • Baan IV
  • Baan V
  • Infor LN

Pre-Configured Dashboards INCLUDED with Crossroads Analytics Dashboard:

  • Accounts Payable
  • Accounts Receivable
  • Journal
  • Booked Sales
  • Invoiced Sales
  • Production
  • Receipts
  • Purchase Orders
  • Inventory

Use these, or create your own!  

Contact Kathy Barthelt to learn more.

Previous Article Infor LN & Baan Tip of the Week: Quantity change during shipment planning – 10.7
Next Article Infor's Support Schedule for Infor LN & Baan
Print
33689 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.