Infor LX & BPCS Materials Tip: Over-Receipts

If Infor LX is set up to prevent over-receipts, you cannot post a receipt quantity that is more than the remaining PO line quantity with the over-tolerance % added to it.

As an alternative, you can:

  • Receive the maximum, remaining line quantity plus over-tolerance percentage quantity, and reject the balance to quarantine or
  • Receive the full quantity into quarantine.


Note: Over-receipt checking applies only to receipts to stock.

Previous Article Infor LN & Baan Tip of the Week: Limitations of Customer Defined Fields (CDFs)
Next Article Infor LX & BPCS Manufacturing Tip: Shop Calendar Maintenance – SFC140D1
Print
28734 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.