Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Infor ERP Tip: Is your Infor ERP system up to date with all of the sales tax changes for 2021?

Infor LX, BPCS, Infor M3, Infor LN & Baan

Want a way to ensure that your Infor ERP system is always using the correct tax rates? 
Here's the tool to help: 2021 Sales Tax Rates 

Contact Crossroads RMC to learn how the Avalara - AvaTax integration can benefit your company. 800.762.2077​

Previous Article Get Tax Compliance Right in 2021!
Next Article Avalara - AvaTax Integration to Infor LX, BPCS, Infor LN, Baan, and M3
Print
36718 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.