What problem is OTTO addressing?

Most manufacturers are being pressured to reduce delivery lead-times and rely on their planning systems to meet their commitments. This works very well if everything happens as planned. But planning by itself doesn’t make things happen, people and processes make things happen. This acceleration is putting tremendous pressure on key users like planners, schedulers, buyers and production supervisors. Not only are they struggling to meet daily commitments and relying on “brute force” solutions to get the job done but they can actually become unrecognized production constraints. Planning is more important than ever but is no longer sufficient to meet current challenges because the real challenge in meeting commitments isn't planning but in making plans happen.

This is where OTTO comes in - Learn More>

Previous Article Analytics Dashboard: "The real voyage of discovery consists, not in seeking new landscapes, but in having new eyes." – Marcel Proust
Next Article IDF News: Multi-Language Support
Print
28974 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.


To calculate the offset, the system takes the parent lead time from the Item 
Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.


Note that the offset calculation uses only calendar records that have a blank 
work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program SFC140, in your Shop Floor Control documentation for shop calendar details.

You can integrate Accounts Payable (ACP) with Purchasing. ACP requires more detailed information in the Vendor file than Purchasing requires. Accounts Payable automatically checks for a valid purchase order when you

match invoices to POs and receipts. Enter any outstanding active purchase orders through PO Release, PUR500, before you can match invoices in Accounts Payable.

 

Accounts Payable can also update the Actual Cost fields in the Inventory Master file directly from vendor invoices. You must provide the following information in order for Accounts Payable to complete this update:

▪ Define a type C inventory transaction.

▪ Enter a valid purchase order on the Invoice Entry header screen, ACP500D2-01, or in the Next Purchase Order field on the Invoice Entry: PO Costing screen, ACP500D3-01.

▪ Enter the information for the actual cost transaction on the appropriate lines.