Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both.

  • Independent Demand: This refers to demand that originates from sources such as forecasts or actual customer orders. Items sold directly to customers fall under this category.
  • Dependent Demand: Derived from higher-level demand within the product structure, dependent demand comprises components, raw materials, and sub-assemblies. These items are not typically designated as Master Scheduled Items.
  • Service Parts may exhibit both independent demand, originating from forecasts or customer orders, and dependent demand, stemming from their use in other sub-assemblies or products.
  • A crucial concept in MPS is the Cumulative Lead Time, which combines fixed and variable lead times required to produce a product. It represents the longest path through a given Bill-of-Materials (BOM). In Infor LX (ERP LX), the system calculates the cumulative lead time, also known as the Critical Path, based on setup options. Utilize the "indented BOM" display in BOM300 to identify the item with the longest lead time. Additionally, you may need to use Action 21, Line Detail, to view the lead time ("L/T") for each item.
Previous Article Unlocking the Full Potential of Your LX/BPCS Investment - Embrace the Cloud for Enhanced Connectivity
Next Article ​Infor LN & Baan Tip: Determining What Data to Archive or Delete
Print
24744 Rate this article:
5.0

Contact

George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

For years, paper work instructions have been a standard part of manufacturing. They were easy to distribute, simple to update, and familiar to operators.

But manufacturing has changed. Products are more complex, customer expectations keep rising, and as experienced employees retire, new hires often need to become productive faster than ever before. As a result, many manufacturers are rethinking how information is delivered on the shop floor.

The Challenge with Paper

Paper work instructions create several common challenges:

  • Multiple versions of the same document
  • Outdated instructions remaining at workstations
  • Time spent searching for the correct information
  • Longer training periods for new employees
  • Inconsistent processes between operators

On their own, none of these seem like a major problem, but together they add up to real quality and productivity issues.

A Shift Toward Digital Work Instructions

One trend we're seeing across the manufacturers we work with is a move toward digital work instructions. Rather than relying on printed documents, operators receive the latest approved instructions directly at their workstation, along with supporting images, videos, and other visual aids. This helps ensure every operator is working from the same information, every time.

Manufacturers making this shift are also gaining new capabilities they didn't have with paper: capturing production data directly from the shop floor, improving traceability, and supporting standardized work across shifts and facilities.

What Manufacturers Are Reporting

Categories