Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: LN Order Management - Generating Purchase Receipts

The purpose of the option to "Generate" is to insert purchase order lines automatically into the purchase receipt. As part of the automatic process, all receipt lines are also automatically confirmed. The option should be used when large orders are received.   

If necessary, received quantities that are not correct can be adjusted through session Correct Purchase Receipt (tdpur4106s100).

Alternative: From the purchase order lines menu the option "Lines to be Received" can be used. This starts session Purchase Order Lines - To Be Received (tdpur4501m400) with the option "Confirm" on top selected. This option can be deselected and thus unconfirmed purchase receipt lines will be created. Packing slip numbers can be inserted into each purchase receipt line manually and received quantities can still be modified. Hereafter confirming the receipt, the option "Correct Receipt..." will be available for each single selected purchase receipt line.

Previous Article Infor LX & BPCS Tip: What is System i Workspace AnyWhere?
Next Article Mitigating Risk With Your Infor ERP
Print
55086 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Categories