BPCS/LX Tip of the Week: Top Down Shop Order Schedule

In ERP LX, this function is called Backward Scheduling. This is a simple, easy way to create and release shop orders associated with the end item.

The result is a shop calendar with the associated order start dates. Setting up ERP LX properly with correct Queue Times, Setup and Run Times, along with Move Times, will result in accurate shop order start dates.

Previous Article Baan/LN Tip of the Week: Back Dating Cycling Counting Orders
Next Article Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance
Print
75826 Rate this article:
No rating

Contact

Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.

Categories