Baan/LN Tip of the Week: Safety Time


You can add safety time in the item master for the item. This will add the number of days safety time to the order lead time thus bringing the order in x number of days early. (x is the safety time).

The safety time is on form 4 of the item master in Baan IV and in Item Ordering Data – Generation I tab in Baan V and LN.

Previous Article BPCS/LX Tip of the Week: How does ERP LX establish costing for purchased items?
Next Article BPCS/LX Tip of the Week: Batch Allocation
Print
100287 Rate this article:
No rating

Contact

Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.