Baan/LN Tip of the Week: Company Calendar

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

Previous Article BPCS/LX Tip of the Week: SFC600 & SFC650
Next Article Infor and Crossroads RMC are proud to offer a joint webinar on Taking Your Shop Floor Paperless - August 28th, 2014.
Print
77586 Rate this article:
No rating

Contact

Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

Use this session to define simulated purchase prices for purchased items per site.

Field Information:

  • Cost Calculation Code - price calculation code
  • Item

The raw materials, subassemblies, finished products, and tools that can be purchased, stored, manufactured, and sold.

An item can also represent a set of items handled as one kit, or which exist in multiple product variants.

You can also define nonphysical items, which are not retained in inventory but can be used to post costs or to invoice services to customers. The examples of nonphysical items:

  • Cost items (for example, electricity)
  • Service items
  • Subcontracting services
  • List items (menus/options)
     
  • ​Site - The site for which the purchase price is simulated.
  • Purchase Currency - The currency of the simulated purchase price.
  • Simulated Price - Purchase price

The simulated purchase price and currency are recorded twice.

  • Simulated Price Multi Currency - The purchase price in multiple currencies.

The simulated purchase price and currency are recorded twice. The amount in this field is related to the price of the supplier.

  • Unit - Purchase price unit
  • Cost Component - The cost component that must be of the type Material Costs.

Note: The cost component specified in this field does not become part of the standard cost detail structure if it is part of the cost component scheme of the selected item. If calculations are performed with a calculation code not used for actualization (simulations only), the simulated purchase price is mapped to the cost component defined in the records for this session.