Baan/LN Tip of the Week: Project Templates

Kathy Barthelt 0 195076 Article rating: No rating

Project templates are useful because you can specify all of the information that you would normally want to include when creating a new project such as project structure, budget and so on.

In Baan IV/V, project templates do not exist, but you can set up a project template by creating a regular project, and setting the status to simulated or free. This is done so that the project does not create plans. Under this scenario, you can easily copy one project to another.

In LN, when you create a new project, a template can be used as the starting point. This is similar to copying a normal project, but unlike normal projects, no costs or revenues can be posted on a template.

Optimize Your Manufacturing Today!

 

Infor LX and Crossroads MES Selected by Blonder Tongue

Crossroads RMC 0 33633 Article rating: No rating

Blonder Tongue, a global communication equipment supplier for TV broadcasters, cable system operator, lodging video, Internet system, and institutional systems, has selected Crossroads RMC to assist them with a BPCS 6.0.04 upgrade to Infor LX. Crossroads RMC will be providing all applications and technical consulting for this project. Also included as part of the project will be the implementation of the Crossroads MES solution. Go live for both solutions is expected in January of 2018.

BPCS/LX Tip of the Week: LX 8.3.5 Facility Period Close

Anthony Etzel 0 46278 Article rating: 5.0

The Facility Period Close process was introduced in Infor LX 8.3.4 and has been enhanced in 8.3.5. This feature allows continuous or 24-hour worldwide operations in multiple facilities to submit Period End Close jobs for each facility as daily operations cease, or shifts end.

This enhancement provides a batch mode for the Facility Period Close (INV930) process and allows the Update IIM Inventory from IWI (INV931) process to be submitted from the INV930B program. The enhancement also provides a batch mode for the INV931 process.

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: Order Series Full – Switching to a Different Series

Kathy Barthelt 0 188027 Article rating: 5.0

In general, you can enter a different series in the order field if you have an available series.

To add a new series, find the appropriate group in the First Free Number session, and add a new series and first free number (usually 1).

In Baan IV, go to the Maintain First Free Numbers Session (under Common, Tables, Maintain Logistics Tables, Maintenance 1).
Groups are easily identified (e.g., Purchase Order, Sales Order, etc.).

In Baan V, go to the First Free Number Session (under Common Data, Tables, Logistics). There are number groups (e.g., 570 may be for Purchase Orders, 650 may be for Sales Orders, etc.).

In LN, go to the First Free Number Session (tcmcs0150m000 – it is in different places in the menu under different Feature Packs). There are number groups (e.g., 210 may be for Purchase Orders, 310 may be for Sales Orders, etc.).

BPCS/LX Tip of the Week: Revisit The Last Brilliant Idea

Anthony Etzel 0 48945 Article rating: No rating

Sometimes the best ideas have to be tabled due to competing priorities. That doesn’t mean that the idea was bad. Revisit previously suggested cost savings ideas, or ideas to make a manual process more efficient. Now could be the right time to do something great!

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: Difference Between a Serialized Item and Unit Effective Item

Kathy Barthelt 0 137580 Article rating: No rating

A serialized item is not the same as a unit effective item. A serialized item has a serial number that is used to identify and track individual items, whereas a unit effectivity item has an effectivity unit that provides some information about the item's configuration. However, an item can be both serialized and unit effective.

Optimize Your Manufacturing Today!
 

Baan/LN Tip of the Week: Alternative Materials in BOMs:

Kathy Barthelt 0 417668 Article rating: No rating

Often, multiple items are interchangeable even when these are purchased from various vendors. You can use any of these items as material in a bill of material (BOM). If a shortage of a standard material is expected to delay a production order, LN can automatically select one of the alternative materials. You can define up to nine alternative materials for any material in a BOM.

The use of alternative materials has the following advantages:

  • LN can handle material shortages for some items without user intervention.
  • The use of alternative items can reduce the average inventory level.

BPCS/LX Tip of the Week: Purchase Order “In Use” Reset Feature 8.3.5

Anthony Etzel 0 44194 Article rating: No rating

 

This new feature provides the ability to resolve or reset a purchase order or requisition that is no longer being processed, but the system still indicates it is ‘in use’. We all remember those situations where we could never figure out how the order got hung up.

What we previously had to do was run a behind the scenes script to reset the flag so the order was again accessible. This enhancement provides the ability to resolve the issue and resume processes quickly.

This option is now on the PUR menu, and the user can select the Purchase Order/Requisition in Use Maintenance, PUR940D. The user then enters an order or requisition to remove the “In Use” status.

 

Optimize Your Manufacturing Today!

First91929394969899100Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Anthony Etzel
/ Categories: Infor LX & BPCS Tips

BPCS/LX Tip of the Day: LX Inventory Pallet Status Flow

Four fields in the Item/Warehouse record (IIW file) affect the disposition of the

pallet status.

 

1.  Goods Receiving Code: You define these codes in Goods Receiving Maintenance (WHM130). The codes control whether or not the stock passes through inspection, what percentage, or quantity of a delivery to inspect, and the number of quarantine days, if any.

 

2.  Inspection Zone/Inspection Location: Either the Inspection Zone or the Inspection Location must be entered on the Item/Warehouse Master Maintenance screen WHM150D2-01.

 

3.  Default Inventory Status: If the status is 0 (Received) or 1 (Inspection), the item moves from the receiving location to the inspection location in inspection status. If the pallet status is not 0 or 1 (that is, 4 (Available) or 9 (Rejected)), the pallet moves to the inspection location with the default status, but the pallet will not proceed from the Inspection location to the Putaway location. You must manually move the stock.

 

4.  Pallet Status Codes: 0 (Received), 1 (Inspection), 4 (Available), and 9 (Rejected) are the only pallet status codes reserved by the system to update and advance inventory/pallet status. To do this Warehouse Management uses the following rules:

 

·    Rejected inventory goes from receiving to a Reject (type 9) Location with a Location Type A (Rejected) in the Location Extension file (ILE) record. All inventory received into a reject location is set to a pallet/inventory status of Reject (9).

·    Inventory received by Goods Receiving (WHM510) into a Receiving Location takes on the Default Inventory Status that is in the Item Warehouse file (IIW) record.

·    If the Default Inventory Status is 0 (Received), the system places the pallet status at 0 (Received) in the Receiving Location, I (Inspection) in the Inspection Location, and 4 (Available) if moved from Inspection to any palletized location other than rejection. If moved to rejection the Default Inventory Status changes to 9 (Rejected).