Baan/LN Tip of the Week: Order Series Full – Switching to a Different Series

Kathy Barthelt 0 169051 Article rating: 5.0

In general, you can enter a different series in the order field if you have an available series.

To add a new series, find the appropriate group in the First Free Number session, and add a new series and first free number (usually 1).

In Baan IV, go to the Maintain First Free Numbers Session (under Common, Tables, Maintain Logistics Tables, Maintenance 1).
Groups are easily identified (e.g., Purchase Order, Sales Order, etc.).

In Baan V, go to the First Free Number Session (under Common Data, Tables, Logistics). There are number groups (e.g., 570 may be for Purchase Orders, 650 may be for Sales Orders, etc.).

In LN, go to the First Free Number Session (tcmcs0150m000 – it is in different places in the menu under different Feature Packs). There are number groups (e.g., 210 may be for Purchase Orders, 310 may be for Sales Orders, etc.).

BPCS/LX Tip of the Week: Revisit The Last Brilliant Idea

Anthony Etzel 0 48436 Article rating: No rating

Sometimes the best ideas have to be tabled due to competing priorities. That doesn’t mean that the idea was bad. Revisit previously suggested cost savings ideas, or ideas to make a manual process more efficient. Now could be the right time to do something great!

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: Difference Between a Serialized Item and Unit Effective Item

Kathy Barthelt 0 135061 Article rating: No rating

A serialized item is not the same as a unit effective item. A serialized item has a serial number that is used to identify and track individual items, whereas a unit effectivity item has an effectivity unit that provides some information about the item's configuration. However, an item can be both serialized and unit effective.

Optimize Your Manufacturing Today!
 

Baan/LN Tip of the Week: Alternative Materials in BOMs:

Kathy Barthelt 0 403613 Article rating: No rating

Often, multiple items are interchangeable even when these are purchased from various vendors. You can use any of these items as material in a bill of material (BOM). If a shortage of a standard material is expected to delay a production order, LN can automatically select one of the alternative materials. You can define up to nine alternative materials for any material in a BOM.

The use of alternative materials has the following advantages:

  • LN can handle material shortages for some items without user intervention.
  • The use of alternative items can reduce the average inventory level.

BPCS/LX Tip of the Week: Purchase Order “In Use” Reset Feature 8.3.5

Anthony Etzel 0 43802 Article rating: No rating

 

This new feature provides the ability to resolve or reset a purchase order or requisition that is no longer being processed, but the system still indicates it is ‘in use’. We all remember those situations where we could never figure out how the order got hung up.

What we previously had to do was run a behind the scenes script to reset the flag so the order was again accessible. This enhancement provides the ability to resolve the issue and resume processes quickly.

This option is now on the PUR menu, and the user can select the Purchase Order/Requisition in Use Maintenance, PUR940D. The user then enters an order or requisition to remove the “In Use” status.

 

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: Advantages / Disadvantages of Virtualization

Kathy Barthelt 0 139050 Article rating: 5.0

I know a lot of our customers are considering virtualization projects. I came across this, and thought it might be useful:

The advantages of virtualization include the following:

• You get more out of your existing resources. Pool common infrastructure resources and break the legacy “one application to one server” model with server consolidation.

• You can reduce datacenter costs by reducing your physical infrastructure and improving your server to admin ratio. Fewer servers and related IT hardware means reduced real estate and reduced power and cooling requirements. With better management tools, you can improve your server to admin ratio so personnel requirements are reduced.

• You can increase the availability of hardware and applications for improved business continuity.

• Securely back up and migrate entire virtual environments with no service interruptions. Eliminate planned downtime and recover immediately from unplanned issues.

 

• Gain operational flexibility. Respond to market changes with dynamic resource management, faster server provisioning, and improved application deployment.

The disadvantages of virtualization include the following:

• Virtualization adds overhead to the CPU, memory, IO, and network.

• Virtualization adds an additional layer to the hardware and software stack. Therefore, additional complexity is introduced in the following circumstances:

  • When sizing the physical server.
  • When planning VM capacity.
  • When planning multiple VMs on the same physical server.
  • When investigating performance issues.

 

Baan/LN Tip of the Week: Setting Up Interest Invoicing

Kathy Barthelt 0 106917 Article rating: No rating

You can set up interest invoicing in Accounts Receivable and in the General Ledger.

To set up interest invoicing, use these sessions:

Invoice-to Business Partner (tccom4112s000)
For invoice-to business partners for which you want to raise interest invoices, select the Charge Interest checkbox.

Mapping Scheme (tfgld4573m000)
Use this session to define the mapping of the Interest Invoice / Revenues Analysis integration document type.

Interest Percentages (tfacr5102m000)
Use this session to define the interest percentages for each financial business-partner group, and for different periods of days.

Interest Invoice Related Data (tfacr5101s000)
Use this session to define whether interest must be calculated on unpaid invoices, partly paid invoices, interest invoices, and/or fully paid invoices. You can also indicate that LN must take advance payments, unallocated payments, and credit notes into account for the generation of interest invoices.

Optionally, set conditions
Example: LN only generates an interest invoice advice entry if these conditions are met: The total of all advice entries in one currency is higher than the allowed minimum amount of an interest invoice defined in the Minimum Amount for Interest Invoice field.

The invoice is overdue for a greater number of days than the number of days defined in the Minimum Days for Interest Invoice field.

First9091929395979899Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Collaborate IN-PERSON With Infor LN Users

LN North America User Group - Face-to-Face 2022 (lnnaug.org)

Registration is open for the face-to-face LN North America User Group Annual Meeting!

Things are finally turning around and opening up! We're looking forward to the day when the pandemic stays firmly in the rearview mirror.

It's definitely exciting to be buttoning up the details of the agenda for this event. This is our chance to discuss successes and roadblocks with one another.

This is also an opportunity to spend time with the Infor team. We will have members of the Product Management and Product Development team in-house for presentations, discussion, and questions.

Catch this: Marco Hoogenraad & Bram Vijfhuizen are scheduled to join us on-site!

Seats are limited. Registration closes on April 8th or sooner if we hit that limit.

Don't miss out, register today! We are looking forward to seeing everyone again and hope to see YOU there!

Curious about the agenda? Find it here: https://www.lnnaug.org/events-underway/agenda

Catch the details:

When: 2 full days | April 19 & 20, 2022

Sponsored dinners: April 18 & 19

Registration fee: To attend this event, there is NO COST to customers other than arranging and covering their own travel & lodging at a hotel in Columbus, Ohio.

Registration: Registration is open!

Agenda: The agenda will be a mix of learning sessions, customer stories, discussion groups, and networking time. If you have any questions shoot us an email at lnbaan.naug@gmail.com.

Travel Information

Where: Columbus, Ohio | Brookshire: The Venue at 405 Greif Pkwy, Delaware, OH 43015

Airport Code: CMH - a 20-minute drive from this airport to local hotels. 10 minutes from the hotel to the event location.

Hotels
Cambria Hotel Columbus - Polaris | 9100 Lyra Drive, Columbus, OH, 43240, US | Phone (614) 841-9100 Fax (614) 841-9107
Hilton Garden Inn | 8535 Lyra Dr, Columbus, OH 43240 | Phone: (614) 846-8884
Other hotels that are in Polaris, Columbus, OH would work fine as well.

Print
25301 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories