Infor LX & BPCS Manufacturing Tip of the Week: Backward Scheduling

George Moroses 0 31111 Article rating: 5.0

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers...

Infor LN & Baan Finance Tip: How to clear balances on invoices that will be moved to a new company

Kathy Barthelt 0 71871 Article rating: 5.0

To clear out the balances of outstanding invoices that will be added into new companies or moved into new companies, credit notes could be created for them and have them linked to all the invoices of one customer/supplier. 

Another option is to...

Crossroads RMC's support team is friendly, well trained, experienced, and committed to resolving your support & technical issues as quickly & effectively as possible.

Crossroads RMC 0 26997 Article rating: 5.0

How good would you feel if you knew that 30+ years of ERP manufacturing experience was on the other end of the phone when you placed a support call?

That’s what our customers get when they call Crossroads RMC for help.

Crossroads RMC offers a number of services to help you make the most of your Infor ERP investment, regardless of the version of Infor LX, BPCS, Infor LN, Baan, or Infor M3, you are running. Our support team is friendly, well trained, experienced, and committed to resolving your support and technical issues as quickly and effectively as possible. To ensure all your support needs are met, we offer several different methods:

  • TELEPHONE SUPPORT:
    Our phones are answered by live representatives to ensure that you receive prompt, personal, and efficient assistance. These services are available Monday through Friday 8:30 am to 5:00 pm ET. We also offer standby support and after-hour support when requested.
  • ONLINE SUPPORT:
    Online support is available by logging onto your system using a remote connection. With a live connection, our consultants are able to view your system and troubleshoot issues in real-time.
  • REMOTE & ON-SITE CONSULTING:
    Consulting is an excellent option if more in-depth service, training, or troubleshooting is needed. End-User training or group custom training on new features and solutions is also handled effectively using this method of support.
  • BUSINESS ASSESSMENTS:
    Experienced Crossroads RMC Consultants will compare your existing business processes with your existing software and put together a detailed report of their findings. This includes recommendations for improving the day-to-day running of your business while getting the maximum benefit from your software. This also ensures that you are up to date with any features and technologies without adding disruption to your business.

Learn more about our support services>

Infor LN & Baan Tip: Performance Standard Cost

by Infor

Kathy Barthelt 0 80231 Article rating: 5.0

Everything you ever wanted to know about Calculating Standard Cost and Actualizing Standard Cost / Revaluing Inventory (ticpr2210m000 | ticpr2220m000)

Calculating standard cost and re-valuing inventory are important capabilities within your Infor ERP system for a variety of reasons. Sometimes these sessions experience performance issues. Here is a brand new PowerPoint released by Infor to discuss both the functional and technical side of these sessions. Get every last what, where, why, and how answered so that you can improve how these sessions run on your system.

Download Infor PowerPoint>

First4849505153555657Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

George Moroses

Infor LX & BPCS Manufacturing Tip: Shop Calendar Maintenance – SFC140D1

Shop calendar maintenance, SFC140D1 This program features multiple-level shop calendar maintenance. You can maintain a shop calendar at the global, facility, or work center level. Global level entries override default values found in Work Center Maintenance, CAP100D1, for any program that uses the shop calendar.

Facility overrides affect all work centers in a Facility and are exceptions to the global level. Exceptions defined at the Facility level apply to all work centers for the facility. Work Center calendar entries are the most specific. These entries apply to a single work center and override any Global or Facility conditions.

If you have deleted a work center in Work Center Maintenance, CAP100D1, you cannot delete its shop calendar. The system treats the work center shop calendar like a global calendar for that year. If you try to delete it, you will delete the global shop calendar for that year.

Range processing provides daily or weekly maintenance of all overrides for a period of up to one year with a single command.

The following explains how Infor LX uses calendars for manufactured and purchased parts planning:

  • Infor LX treats purchased and manufactured parts in the same way.
  • Infor LX does not use the work center calendar.
  • In facility planning, Infor LX uses the facility calendar.
  • If the global calendar has additional days blocked out relative to the facility calendar, MRP/MPS plans consider both the facility and global days-off.


In all cases, the system uses the item master/CIC lead time parameter to determine the release date for the planned order regarding the due date from the forecast or parent demand. The system considers days blocked out in the facility and global calendars when it determines the planned order release date.

Example: Assume the entire system (Global) has a specific date set as a regular workday. If one particular Facility recognizes this day as a holiday, no hours are available on work centers within that facility. If conditions at one work center are an exception to this holiday, that work center can be maintained with its own set of conditions.

Simulation Mode

The Shop Calendar Selection/Maintenance Simulation program, MRP747B, uses the Shop Calendar Maintenance programs, SFC140D, in a simulation mode. The MRP program allows you to maintain shop calendar information to simulate capacity planning and to view the results before you use the data in live capacity planning.

When you run MPS by facility, you cannot maintain global calendars. This safeguard prevents a user from unintentionally overwriting the live global calendar if the user runs Copy to Live, MRP770D.

Access: Menu SFC

Print
30177 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

x

Categories