Infor LN & Baan Tip: What conditions must exist before changing an item's inventory unit?

Kathy Barthelt 0 55988 Article rating: 5.0

Is there a procedure for changing an item’s inventory unit? What conditions must exist before it can be done?

Once inventory transactions (receipts or issues) have occurred for an item, the inventory unit cannot be changed. If only orders have been placed against the item (sales or purchase), the inventory unit can be changed if these...

Infor LX & BPCS Tip: 4 Approaches to Customizing LX / BPCS - Preparing for a Future Upgrade

George Moroses 0 22316 Article rating: 5.0

How do I modify BPCS/LX to allow for the ease of upgrading in the future?

  1. Exit Points...

Is it time to get more out of your ERP?

Crossroads RMC 0 12811 Article rating: 5.0

As crazy as it sounds, we’re about to enter the 2nd half of 2023. How are you doing on your 2023 goals? Planning for 2024 projects?
Maybe it's time to get more out of your Infor ERP system.

OFF SUPPORT AND MAINTENANCE WITH INFOR AND FEEL STUCK?

⇒⇒ TIME TO UPGRADE?

⇒⇒ NOT UPGRADING?

Infor LX & BPCS Tip: Support for IBM i 7.3 and Infor LX Products

George Moroses 0 20098 Article rating: 5.0

On September 30, 2022, IBM® announced the end of support of IBM i operating system 7.3 effective September 30, 2023. In line with IBM’s support policy, Infor will no longer support LX and related products on IBM i 7.3 after May 31, 2024. All Infor LX releases, patches, and related solutions are...

Have You Heard About the Latest & Greatest Way to BOOST Productivity?

LIFE HACKS

Kathy Barthelt 0 23237 Article rating: 5.0

In a world of life hacks and constantly changing routines, we could all use help boosting productivity.

With Crossroads RMC support services, boosting your productivity just got 10x easier! Boost the productivity of your entire team by adding just ONE team member that you only pay when you need them. And the best part is that they are waiting for your call right now and every hour of every day, even on weekends and holidays.

Check out Crossroads RMC's Support Services Designed YOUR Way: ...

First2324252628303132Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for EXECUTIVES:

Operations: Copying EBOMs - Which copying method should I use?

To determine which copying method you must use, answer question 1 and follow the instructions.

Question 1: Is the source component a project item (that is, is a project defined in the first segment of the item code)?

  • If the answer is yes, proceed with question 3.
  • If the answer is no, proceed with question 2.


Question 2: Is the target component a project item?

  • If the answer is yes, select copy method NonProj Item to Proj Item.
  • If the answer is no, proceed with question 4.

Question 3: Is there a relationship with the same project?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, proceed with question 4.


Question 4: Is there a relationship with the target item?

  • If the answer is yes, proceed with question 5.
  • If the answer is no, select copy method No Copy Action.


Question 5: Does the item exist already?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, select copy method Copy E-Item to Item.

Technology: Using audit files in the Exchange module

The audit server logs all database actions that change the contents of a table in so-called audit files. The Exchange module can use these audit files, which are useful in a multisite environment because the databases on all sites must have identical data. These audit files can also be used in data conversions.

Only the updates in a specific period are exchanged, which leads to an improvement in performance. Specify this period in the Export Data (Non-Regular) (daxch0233m000) and Export Data (on a Regular Basis) (daxch0234m000) sessions. Changes such as insert, update, and delete are processed and written into the ASCII files. Actions such as drop, clear, and create tables are ignored.

Audit control data is added to the resulting ASCII file. This data consists of a batchline ID, transaction ID, sequence ID, and an indicator. The control data is added at the beginning of each line and is formatted like other data fields such as the enclosing and separator characters.

An update writes two lines to the ASCII file. One line contains the key fields and old values of the updated fields. The other line contains the new values of the key fields and updated fields, even if a key field does not change.

The batchline ID is used for recognition when processing the ASCII files. The transaction and sequence IDs are used to ensure that the transactions are replayed in the same order as on the exporting site. The indicator defines the type of action that is executed on the table. Use the letter I to insert; use the letter D to delete; use the letter U to update with old values; and use the letter N to update with new values.

Finance: Problem Invoices

You can use a problem code to indicate that a problem exists for a sales invoice. If the invoice-to business partner notifies you about a problem with the invoice and does not pay it, you can link a problem code to the invoice.

In the direct debits procedure, problem invoices are automatically discarded. For each problem code, you can set an option to prevent linked invoices from being selected on reminder letters.

Previous Article Infor LN & Baan Tips & Tricks: Action Required - Infor LN Cloud Edition - Fonts Update!
Next Article Infor LN & Baan Tips & Tricks for Operations: Copying EBOMs - Which copying method should I use?
Print
50505 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories