Infor LN & Baan OPERATIONS Tip: MPS Planned vs. MRP Planned

Kathy Barthelt 0 37292 Article rating: 5.0

When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

  • Master Scheduled Items:

    • Master Scheduled Items are typically finished goods or service items.
    • These items receive their requirements from both Independent and Dependent demand sources.
       
  • Independent Demand:...

Infor LN & Baan FINANCE Tip: Is it possible to upload accounts receivable invoices into LN using Excel?

Kathy Barthelt 0 27981 Article rating: 5.0

Yes, this is possible, by following the steps below:

1. Maintain a batch

2. Maintain an invoice headerexport it, add an additional invoice header to the Excel file, and import it

3. Maintain an invoice line for the first invoice, export it, add additional invoice lines to the Excel file and import it
 

Below the above steps are described in detail...

Infor News You Can Use | The business case for moving your ERP to the cloud and choosing MT deployment

Kathy Barthelt 0 14104 Article rating: 5.0

As more companies invest in cloud computing for their business software and migrate their ERP systems to the cloud, many are considering whether single-tenant or multi-tenant cloud deployment is the best choice.

In this executive brief, Infor outlines insights from the analyst community on the growth of cloud technology, key distinctions between single- and multi-tenant deployments, and why the multi-tenant option for ERP may be the best move for your business.

Learn more>

Tick-Tock... It's time to get more out of your ERP

Crossroads RMC 0 12615 Article rating: 5.0

As crazy as it sounds, we’re about to enter the 2nd half of 2024. How are you doing on your 2024 goals? Planning for 2025 projects?

Maybe it's time to get more out of your Infor ERP system.

⇒⇒ TIME TO UPGRADE?

Is an upgrade to the latest version of your ERP the goal for 2024/2025? If so, Crossroads RMC brings 40 years of industry experience to the table to ensure that your upgrade achieves the results you’re looking for and does so on time and within budget.

Crossroads RMC's team of expert consultants will:

  • Review your custom components to see what can be eliminated
  • Provide an analysis of the specific benefits that your company can achieve by upgrading
  • Train your users on the latest functionality
  • Support your users on the old version while the project team focuses on the upgrade project
  • Handle the entire upgrade project from start to finish
  • Supplement your existing project team with 1-2 key resources
  • Develop the integration to that 3rd party system that is a MUST-HAVE when you upgrade


⇒⇒ NOT UPGRADING?

Infor LX/BPCS Tips & Tricks for FINANCE: Prevent Voiding of Selected Invoices

George Moroses 0 19815 Article rating: 5.0

This enhancement prevents users from voiding invoices after they have been selected for payment. If a user selects an invoice for payment and another user voids the invoice during the payment process, it can produce erroneous and duplicate records. The ACP500 programs were modified to check the status of an invoice before it can be voided. If the invoice has been selected for payment, a message is generated, and the invoice cannot be voided.

Infor LX/BPCS Tips & Tricks for TECHNOLOGY: Update User Security in IDF

George Moroses 0 22385 Article rating: 5.0

Automatically synchronize security changes from LX to IDF, replacing CPYSECIDF. This new process synchronizes users in IDF with those in core LX security whenever a user’s security settings are changed. When a user is deleted from an LX environment, they can also be automatically removed from the IDF environment. Changes to a user’s access to programs in LX are mirrored in IDF. Access to Companies, Facilities, and Warehouses are also synchronized. Additionally, when Business Roles or Business Units access is changed, all users assigned to those roles or units are updated in IDF security.

Infor LX/BPCS Tips & Tricks for OPERATIONS: Copy Shop Order

George Moroses 0 22683 Article rating: 5.0

In the Shop Order Selection program, action 3=Copy is available. This action allows copying any shop order except for flow orders or campaign orders. Instead of copying from the parent item's bill of material and routing, the new shop order’s materials and operations will be copied from the selected shop order. Note that if the existing shop order is linked to a customer order or line, this linkage will not be copied to the new shop order.

First2223242527293031Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Streamline Your Shipping Processes – Boost Efficiency and Reduce Errors

with RMCship

Are you manually entering shipping data between your Baan or Infor LN system and UPS/FedEx? If so, you’re likely facing challenges with efficiency, accuracy, and wasted time on redundant tasks. We understand these pain points and want to introduce a solution to transform your workflow: RMCship.

According to a recent report by The Manufacturer and IBM, 92% of manufacturers are prioritizing efficiency. However, the manual entry of shipment details—like transportation mode, weight, and tracking numbers—into logistics systems, only to re-enter data back into Baan and Infor LN, is a major bottleneck. This process not only consumes valuable time but also increases the risk of costly errors and delays in shipping and invoicing.

Here’s how RMCship can help:

  • Eliminate Redundant Data Entry: RMCship integrates seamlessly with Baan IV, Baan V, and Infor LN to automatically send shipment details to UPS and FedEx. Once the shipment is prepared, tracking data, freight costs, and other pertinent information are automatically updated with your ERP.

  • Save Valuable Time: By automating data transfer, RMCship can rescue between 1.5 to 2.5 hours per day, 30-50 hours a month.

  • Reduce Errors and Shipping Delays: RMCship removes manual entry, reducing errors and ensuring shipping and invoicing happen promptly. Faster invoicing means improved cash flow and better customer satisfaction.

  • Access Real-Time Shipping Information: With instant updates on shipping details, your customer service team can access real-time information to enhance customer communication.

Why RMCship?

RMCship offers a complete integration solution for Baan and Infor LN systems, enabling you to streamline your shipping processes from start to finish. With on-premise and cloud deployment options, RMCship adapts to your needs, whether you're handling single, partial, or multiple order shipments per carton or pallet.

Don’t let inefficiencies hold you back. Automate your shipping workflow with RMCship, and see the difference in operational speed, accuracy, and customer satisfaction.

Give us a quick call or request a demo to discuss how RMCship can specifically benefit your operations!

800.762.2077 

Request a demo


 

Print
16649 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories