Infor LN & Baan Tips & Tricks for OPERATIONS: Order Quantity Dependent Routings vs Default Routings

Kathy Barthelt 0 18796 Article rating: 5.0

Order quantity-dependent routings

An automatically selected routing tailored to a specific production order quantity is useful. An example would be if the production order quantity is large, a routing with high production rates is used; If the order quantity is small, another routing is selected.

You can set up these quantity-dependent routings:

Infor LX/BPCS Tips & Tricks for OPERATIONS: Track all order holds added & released

George Moroses 0 14607 Article rating: 5.0

Enhancement: Order Hold Audit Functionality

This enhancement introduces an audit file to track all holds added or released for customer orders. The audit file includes details for various types of holds: credit hold, margin hold, customer hold, user hold, and credit card hold. All applications that add or release a hold now write an audit record, capturing the user, date, time, and program associated with each hold action.

A new IDF Order Hold Audit Inquiry application allows users to review holds based on various criteria:

  • Hold type
  • User
  • Specific order
  • Transactions for a customer within a date range
  • Other combinations

Additionally, the selected data can be printed if desired.

Infor LN & Baan Tip & Tricks for TECHNOLOGY: Infor LN Rest API

Kathy Barthelt 0 20371 Article rating: 5.0

Frequently Asked Questions (KB2316174)

For Infor LN a framework has been developed to support REST API-based services for lean integrations. This framework is now made available for the LN application. This KB answers some common questions you may have and procedures that are needed for using the LN Rest APIs.

More details on these topics can be found in the Infor LN REST API Administration Guide.

Infor LN & Baan Tips & Tricks for EXECUTIVES

Kathy Barthelt 0 20793 Article rating: 5.0

FINANCE: Can accounts receivable invoices be uploaded into LN using Excel?
Yes, this is possible, by following the steps below:

1. Maintain a batch

2. ....

OPERATIONS: MPS Planned vs. MRP Planned
When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

Master Scheduled Items:

TECHNOLOGY: Are you running the latest Infor components?
Always good to stay on top of new releases for your various Infor components. Here is a list of knowledge base articles that you can check for the components listed below:

Infor LX / BPCS Tips & Tricks for EXECUTIVES

George Moroses 0 11236 Article rating: 5.0

FINANCE: Prevent Voiding of Selected Invoices
This enhancement prevents users from voiding invoices after they have been selected for payment. If a user selects an invoice for payment and another user voids the invoice during the payment process, it can produce erroneous and duplicate records. The ACP500 programs were modified to check the status of an invoice before it can be voided. If the invoice has been selected for payment, a message is generated, and the invoice cannot be voided.

OPERATIONS: Copy Shop Order
In the Shop Order Selection program, action 3=Copy is available. This action allows copying any shop order except for flow orders or campaign orders. Instead of copying from the parent item's bill of material and routing, the new shop order’s materials and operations will be copied from the selected shop order. Note that if the existing shop order is linked to a customer order or line, this linkage will not be copied to the new shop order.

TECHNOLOGY: Group Security for ILM501 Inbound Delivery Maintenance
Add function key / action code security to control who is authorized to create/revise/delete functions in ILM501 Inbound Delivery Maintenance.  With added Group Security, managers can control which users are authorized to create, change and delete deliveries in ILM501 Inbound Delivery Maintenance.

Infor LN & Baan OPERATIONS Tip: MPS Planned vs. MRP Planned

Kathy Barthelt 0 31129 Article rating: 5.0

When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

  • Master Scheduled Items:

    • Master Scheduled Items are typically finished goods or service items.
    • These items receive their requirements from both Independent and Dependent demand sources.
       
  • Independent Demand:...

Infor LN & Baan FINANCE Tip: Is it possible to upload accounts receivable invoices into LN using Excel?

Kathy Barthelt 0 22322 Article rating: 5.0

Yes, this is possible, by following the steps below:

1. Maintain a batch

2. Maintain an invoice headerexport it, add an additional invoice header to the Excel file, and import it

3. Maintain an invoice line for the first invoice, export it, add additional invoice lines to the Excel file and import it
 

Below the above steps are described in detail...

First1112131416181920Last

Tips:  LX | BPCS | M3

George Moroses
/ Categories: Infor LX & BPCS Tips

Infor LX / BPCS Tip of the Week: Control Date Lead Times in LX

  • Control Date Lead Times – LX provides five separate Control Date Lead Time fields so you can specify additional lead time values for Shop Orders, Purchase Orders and Planned and Firm Planned orders. Each Control Lead Time Date represents additional time (days) required at each step in the process that needs more time (Quarantine, Stabilize), that is to say, when a component is due, and when it can be used. (working with an aerospace  precision bearing manufacturer, I had to account for the QA requirement that no measurements could be taken until the parts had been “soaked” (stored) in an atmospheric controlled environment (72 degrees, and controlled humidity) for 24 hours. This requirement added one full day of lead time between each machining operation) The MPS/MRP Generation program, as well as programs that Shop Order Material Allocation records use the five control date lead times to adjust component required dates to function in the same way as the BOM Offset Lead Time.
     
  • All programs that create MRP Planned Orders, MRP Firm Planned Orders, Shop Orders, and Purchase Orders call the Control Date Calculation program (MRP515B) to establish all five control dates. A Control Lead Time Date is used to adjust the component Required Dates data in the Material Requirements file (KMR), based on planned orders for a parent, and the FMA Required Dates data, based on shop order release dates for a parent.
Previous Article Infor LX & BPCS Tip of the Week: Control Number, POCNO, added to CEA502B1
Next Article Infor LX & BPCS Tip of the Week: What is EGLi?
Print
56820 Rate this article:
5.0

Contact

George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

x

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.