BPCS/LX Tip of the Week: Uses for LX Bill of Material

Anthony Etzel 0 92107 Article rating: No rating
In Infor LX, based on how your items are set up and on how you structure the Bill of Material, the following are some usages of a bill of material by functioning area:

  • Engineering & QA – change control, product design and specifications
  • Manufacturing – build instructions , material pick lists
  • Accounting – product costing
  • Materials Inventory – material and inventory planning
  • Sales – customer order processing
  • Production Scheduling – item scheduling (also a component of an MES solution)

Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance

Kathy Barthelt 0 79406 Article rating: No rating
In Baan IV, the order balance amount always includes the tax amount. Consequently, the tax amount must be recalculated every time an order line is modified in order to update the balance correctly. If the tax provider is activated, this requires an API call for every re-calculation of tax.

In Infor LN, users can select or clear the new Include Tax in Order Balance check box in the COM Parameters (tccom0000s000) session to indicate whether users want to include tax amounts in the order balance amount. This parameter has an effect on various sessions in Order Management.

Why Your Operation Doesn’t Stand a Chance in Hell of Going From Good to Great (and What to do About it)

David Dickson 0 112697 Article rating: 5.0

You dream of building a manufacturing powerhouse.

An operation with loads of throughput, profit, and efficiency in every process to make your products the best quality you can make them.

You want to be as successful as the factories and companies they write about in books like  Good to Great, changing your operation, and even motivating and inspiring your teams to do so too.

But you know you haven’t got a chance in hell of seeing that kind of success unless you can truly change and make significant differences over the long haul.

Of course, the big question is How? 

BPCS/LX Tip of the Week: Indirect Labor Reporting

Anthony Etzel 0 82454 Article rating: No rating
In the Shop Floor Control Module, you have the ability to key in both direct labor and indirect labor. However you want to establish specific types (reasons) for the indirect labor. The SFC600 labor entry program shows a reason code field, but it is designed for reject quantity and machine downtime reasons, not indirect labor reasons.

There is a way around this. With an MES solution you have the ability to setup and report indirect time against a specific reason code.

Baan/LN Tip of the Week: Configuring Items in Infor LN

Kathy Barthelt 0 92761 Article rating: No rating

In Infor LN, the configuration of a generic item not always results into a customized item. Configured items can now be customized items as well as standard items. If users configure items without PCS projects, standard items are generated instead of customized items.

Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance

Kathy Barthelt 0 81877 Article rating: No rating
In Baan IV, the order balance amount always includes the tax amount. Consequently, the tax amount must be recalculated every time an order line is modified in order to update the balance correctly. If the tax provider is activated, this requires an API call for every re-calculation of tax.

In Infor LN, users can select or clear the new Include Tax in Order Balance check box in the COM Parameters (tccom0000s000) session to indicate whether users want to include tax amounts in the order balance amount. This parameter has an effect on various sessions in Order Management.

BPCS/LX Tip of the Week: Shop Order Status

Anthony Etzel 0 86370 Article rating: No rating

You can see the status of the Shop Order when using SFC300 Shop Order Inquiry. You want to be sure that your shop orders are at the correct status in order to report against them.

The following are the shop order status codes:

04 = The Shop order has been entered.

05 = The Shop order has been released and printed.

14 = The Shop order has been released, but not printed. If a shop order is at this status, you have released it and it is not printed due to a system failure, or the order has been put on hold.

XX = The Shop order is closed.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 88716 Article rating: 4.0
For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.
First127128129130132134135136Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Use this session to define simulated purchase prices for purchased items per site.

Field Information:

  • Cost Calculation Code - price calculation code
  • Item

The raw materials, subassemblies, finished products, and tools that can be purchased, stored, manufactured, and sold.

An item can also represent a set of items handled as one kit, or which exist in multiple product variants.

You can also define nonphysical items, which are not retained in inventory but can be used to post costs or to invoice services to customers. The examples of nonphysical items:

  • Cost items (for example, electricity)
  • Service items
  • Subcontracting services
  • List items (menus/options)
     
  • ​Site - The site for which the purchase price is simulated.
  • Purchase Currency - The currency of the simulated purchase price.
  • Simulated Price - Purchase price

The simulated purchase price and currency are recorded twice.

  • Simulated Price Multi Currency - The purchase price in multiple currencies.

The simulated purchase price and currency are recorded twice. The amount in this field is related to the price of the supplier.

  • Unit - Purchase price unit
  • Cost Component - The cost component that must be of the type Material Costs.

Note: The cost component specified in this field does not become part of the standard cost detail structure if it is part of the cost component scheme of the selected item. If calculations are performed with a calculation code not used for actualization (simulations only), the simulated purchase price is mapped to the cost component defined in the records for this session.

Categories