BPCS/LX Tip of the Week: Changing the Master Schedule

Anthony Etzel 0 74093 Article rating: 4.5

You can change your master schedule by specifying the type of master schedule update to perform. You can run a Net Change or Regenerative Schedule.

You also have the ability to clear the lower level requirements out of the Planned and Firm-Planned Order file.

Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance

Kathy Barthelt 0 107855 Article rating: No rating

In Baan IV, the order balance amount always includes the tax amount. Consequently, the tax amount must be recalculated every time an order line is modified in order to update the balance correctly. If the tax provider is activated, this requires an API call for every re-calculation of tax.

In Infor LN, users can select or clear the new Include Tax in Order Balance check box in the COM Parameters (tccom0000s000) session to indicate whether users want to include tax amounts in the order balance amount. This parameter has an effect on various sessions in Order Management.

Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 114981 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

BPCS/LX Tip of the Week: What is Lean Make to Order?

Anthony Etzel 0 71781 Article rating: No rating

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

PDIC Goes Live with Crossroads MES

Anthony Etzel 0 52891 Article rating: 5.0

PDIC, a leading producer of wire products, went live with the Crossroads MES solution on June 30th,2014. PDIC needed a better way to deploy and report shop floor information to BPCS 6.02. Their goal was to eliminate all their manual reporting and position themselves to take advantage of the Crossroads Dashboards.

Baan/LN Tip of the Week: Negative Inventory

Kathy Barthelt 0 126352 Article rating: 5.0

If Location Control is turned on in Baan IV, then inventory should never be negative.

If Location Control is not turned on in Baan IV, and the parameter “Negative Inventory Allowed” in INV Parameters is set to “NO”, then inventory should never be negative.

In Baan V and LN, the parameters in Inventory Handling Parameters determine whether you can have negative inventory. If these parameters are set to “NO”, then inventory should never be negative.

BPCS/LX Tip of the Week: Establish Costing For Purchased Items

Anthony Etzel 0 86242 Article rating: No rating

How Does Infor LX Establish Costing For Purchased Items?

In LX, you will establish a standard cost (you define the standard) that LX will use for the purchase items. You also need to establish in LX the Cost Type, the Cost Bucket, and the Cost Set needed for cost accounting.

BPCS/LX Tip of the Week: Alternate Items

Anthony Etzel 0 78350 Article rating: No rating

How can I use an alternate item on a shop order?

The best way is to have the approved alternate item appear on the Bill of Material just after the standard item with a zero required quantity. Now the alternate item will appear on the Shop Order. So, if the standard item is not available, the alternate item can be issued to the shop order.

When the shop order is closed out, one item will have an unfavorable variance while the other shows a favorable variance. This is an easy way to provide alternate items provided engineering approves and they are part of the Bill of Material.

First123124125126127128129131

Tips:  LX | BPCS | M3

Tips: LN | Baan

Avoid Being a Quitter: How Crossroads RMC Can Help You Achieve Your Goals

Unlocking Success Infor LX/BPCS & Infor LN and Baan

Avoid Being a Quitter

As the calendar flips to January 1st, it marks the beginning of a new year filled with fresh opportunities and resolutions. It's that time when many of us set ambitious goals for ourselves, both personally and professionally. But, how often do these aspirations fizzle out before we even hit the second Friday of the year? It's so common that they even call it "Quitter's Day." However, it's not too late to stay on track and realize your ambitions. In this article, we'll focus on the professional side of goal-setting and how Crossroads RMC can be your ally in achieving manufacturing excellence.

Step 1: Make Your Goals Bite-Sized

While you might have grand ambitions, like upgrading your ERP system, increasing customer satisfaction, or optimizing your supply chain, achieving these goals often involves breaking them down into smaller, manageable projects. Here's how you can start:

  • Why: Understand why you want to make these changes. Is it to retain your top customers, leverage new ERP features, or streamline your supply chain?
  • What: Clearly define the desired outcomes – be it increased sales, enhanced efficiency, or cost reduction.
  • Who: Identify the key players who can help you achieve these goals. Do you have the necessary resources in-house, or should you consider external expertise?
  • When: Establish a timeline, considering your overall company initiatives, project priorities, and deadlines. Make your goals specific, measurable, attainable, and time-based (SMART).

For example:

  • Increase customer satisfaction for our top 5 customers by 10% in the next 6 months.
  • Reduce production mistakes in our welding department by 50% within a year.


Step 2: Identify Roadblocks

What's preventing you from reaching your goals? Is it a lack of resources, support, or the right tools? Consider these factors:

  • Lack of bandwidth: Assess your team's capacity. Can you involve colleagues from other departments or partners?
  • Support: Get buy-in from business leaders by demonstrating the ROI and benefits of your project. Educate your coworkers on its importance.
  • Tools: Explore features in your ERP system that you might not be utilizing fully. Is an upgrade or additional software add-ons needed?

 
Step 3: Take Action and Persist

Creating a plan is vital, but remember, the path to success isn't always smooth. Prepare for challenges and adapt as needed:

  • Develop a comprehensive plan to execute your goals.
  • Communication is key. Keep your team informed about progress and challenges.
  • Adjust your plan when necessary. Mistakes are part of the journey and can lead to future success.


How Crossroads RMC Can Help You in 2024

At Crossroads RMC, we understand the challenges manufacturers face, and we're here to support your journey to success. Here's how we can assist:

  • Implement new functionality in your existing ERP system.
  • Lead the way in upgrading your ERP to the latest version.
  • Provide training based on best practices for your employees.
  • Automate time-consuming, manual processes.
  • Integrate your systems, creating a seamless, cohesive environment.
  • Deliver ERP add-on solutions that save you time and money.

We offer a comprehensive range of consulting services and software designed to optimize manufacturing by reducing costs, improving quality, and enhancing efficiency.

Learn More:

Infor LX & BPCS Services> Infor LX & BPCS Software>

Infor LN & Baan Services> Infor LN & Baan Software>
 

It's Time for Action!

Contact us today at solutions@crossroadsrmc.com or call us at 800.762.2077 to discuss your ERP goals. Let Crossroads RMC be your partner in making 2024 a resounding success for your manufacturing business!

Print
14617 Rate this article:
.2
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

x

Categories