BPCS/LX Tip of the Week: Work Center - Cells

Anthony Etzel 0 86682 Article rating: No rating
The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.

BPCS/LX Tip of the Week: The Machine Master Part 2

Anthony Etzel 0 83623 Article rating: No rating
Understanding:

The Machine Master File

Do your machines have a fixed asset tag? The machine master file has a field called Fixed Asset.

BPCS does not use this field, so you can use this field for anything. You can record your fixed asset tag in this field and use the effective date. You can create a custom fixed asset list by using a DFU or Query program.

Baan/LN Tip of the Week: Business Partner Structures

Kathy Barthelt 0 89177 Article rating: No rating

In ERP LN, users can define a distributed business partner organization by defining parent business partners to link the business partners with different roles.

In Baan IV, users can define a distributed business partner organization in the Maintain Concern Structure of Trade Relations (tccom3101m000) session.

Harsco Rail Goes Live With the RMC3 Data Collection Solution

Crossroads RMC 0 36644 Article rating: No rating

Harsco Rail, an industry leader in the railway track maintenance, has completed the first phase of their implementation of the Crossroads RMC Data Collection Solution for Baan V. The initial implementation included receiving and putaway. Harsco’s data collection project manager reports, “When I ask them (the users) how it’s going, they smile. I have had nothing but very positive feedback. It’s been very uplifting for me to work on this project and have it so well received.” The next phase of the implementation will include Report Operations Complete, Inventory Transfers, and Stock Inquiry.

Baan/LN Tip of the Week: Tax Exemption Certificates

Kathy Barthelt 0 84624 Article rating: No rating

In Baan IV, tax exemption processing is supported only on sales orders for non-tax provider users.

In Infor LN, tax exemption certificate processing is also performed for purchase orders, and for sales orders if users use a tax provider.

Users can define tax-exemption certificates in the following sessions:

  • Tax Exemptions for Sales (tcmcs1142m000)
  • Tax Exemptions for Purchasing (tcmcs1560m000)
  • Register Warehouse for Tax Exemptions (tcmcs1561m000)

 

BPCS/LX Tip of the Week: The Machine Master Part 1

Anthony Etzel 0 82703 Article rating: No rating
Understanding:

The Machine Master File


Machines are associated with a work center. For example, in the work center you may have multiple machines and each machine can have a unique machine ID. If there are several machines that perform the same function, they may operate at different speeds and efficiencies. Setting up the machine master can be a benefit for planning capacity and shop order throughput.

Baan/LN Tip of the Week: Aborted Finalization Run

Kathy Barthelt 0 76517 Article rating: No rating
When a finalization run is aborted and in the batches selected for this finalization run are transaction types having the update mode finalization, you must use the Restart Finalization Run session. This session can be found in the Transaction Processing menu of the General Ledger Module of the Finance Package.

BPCS/LX Tip of the Week: SFC600

Anthony Etzel 0 79781 Article rating: No rating
In addition to SFC650, this ERPLX program is also used to capture and post shop floor information.

The key difference between the two is that SFC600 only captures Labor (run time) reporting, machine time, downtime and indirect time.

If you use SFC600, then all shop order material receipts and issues would be captured using INV500.

Both Inventory and Shop Floor Transaction entry is keyboard dependent, unless you incorporate an automated method like an MES solution to capture the data.
First123124125126128130131132

Tips:  LX | BPCS | M3

Tips: LN | Baan

Companies can decide to involve a subcontractor and subcontract part of their activities. The subcontractor carries out the work and returns the products to your company.

In Infor LN, subcontracting is considered as purchasing labor from a third party. Therefore, if a manufacturer wants to subcontract work, he must generate a purchase order to start the subcontracting process. These are the types of subcontracting:

  • Subcontracting with material flow
    • Operation subcontracting: For operation subcontracting, a part of the production process (one or more operations) is subcontracted.
    • Item subcontracting: For item subcontracting, an item's entire production process is subcontracted. Therefore, it is always used with material flow support.
  • Subcontracting without material flow: The simplest form of subcontracting is to generate a subcontracting purchase order to record the operations outsourced to a subcontractor. The subcontracting purchase order only represents the administrative handling of the subcontracting process. When the subcontracted item is received back from the subcontractor, you must close the subcontracting purchase order, which initiates the production process.
  • Unplanned subcontracting: Unplanned subcontracting is applicable when you subcontract after generating a production order. For unplanned subcontracting, a purchase order is generated from the production order and the material supply lines are populated by Shop Floor Control.
  • Service subcontracting: For service subcontracting, work on an item to be maintained or repaired is subcontracted. This work entails the entire repair process, or only a part of it. Service subcontracting can be used with or without material flow support.

To start the subcontracting process, a purchase order is required.