Harsco Rail Goes Live With the RMC3 Data Collection Solution

Crossroads RMC 0 36505 Article rating: No rating

Harsco Rail, an industry leader in the railway track maintenance, has completed the first phase of their implementation of the Crossroads RMC Data Collection Solution for Baan V. The initial implementation included receiving and putaway. Harsco’s data collection project manager reports, “When I ask them (the users) how it’s going, they smile. I have had nothing but very positive feedback. It’s been very uplifting for me to work on this project and have it so well received.” The next phase of the implementation will include Report Operations Complete, Inventory Transfers, and Stock Inquiry.

Baan/LN Tip of the Week: Tax Exemption Certificates

Kathy Barthelt 0 84324 Article rating: No rating

In Baan IV, tax exemption processing is supported only on sales orders for non-tax provider users.

In Infor LN, tax exemption certificate processing is also performed for purchase orders, and for sales orders if users use a tax provider.

Users can define tax-exemption certificates in the following sessions:

  • Tax Exemptions for Sales (tcmcs1142m000)
  • Tax Exemptions for Purchasing (tcmcs1560m000)
  • Register Warehouse for Tax Exemptions (tcmcs1561m000)

 

BPCS/LX Tip of the Week: The Machine Master Part 1

Anthony Etzel 0 82587 Article rating: No rating
Understanding:

The Machine Master File


Machines are associated with a work center. For example, in the work center you may have multiple machines and each machine can have a unique machine ID. If there are several machines that perform the same function, they may operate at different speeds and efficiencies. Setting up the machine master can be a benefit for planning capacity and shop order throughput.

Baan/LN Tip of the Week: Aborted Finalization Run

Kathy Barthelt 0 76285 Article rating: No rating
When a finalization run is aborted and in the batches selected for this finalization run are transaction types having the update mode finalization, you must use the Restart Finalization Run session. This session can be found in the Transaction Processing menu of the General Ledger Module of the Finance Package.

BPCS/LX Tip of the Week: SFC600

Anthony Etzel 0 79663 Article rating: No rating
In addition to SFC650, this ERPLX program is also used to capture and post shop floor information.

The key difference between the two is that SFC600 only captures Labor (run time) reporting, machine time, downtime and indirect time.

If you use SFC600, then all shop order material receipts and issues would be captured using INV500.

Both Inventory and Shop Floor Transaction entry is keyboard dependent, unless you incorporate an automated method like an MES solution to capture the data.

BPCS/LX Tip of the Week: Downtime Reasons

Anthony Etzel 0 78670 Article rating: No rating

Using SFC600 to enter downtime.

You are tracking downtime and using SFC600 to enter the downtime, but you don’t know where to go to setup downtime reasons. You can set up the downtime reason codes in the INV application by selecting the reason code maintenance program INV140D1.

Once you are in the reason code maintenance program, position to the transaction effect code “D”. Using the transaction effect code “D” you can now setup as many downtime reason codes as needed. The reason code field is alpha numeric, so be creative with your reason code assignments.

Baan/LN Tip of the Week: Restricted User Access

Kathy Barthelt 0 73168 Article rating: No rating
Administrators are able to restrict access in Baan in several ways – including Companies, Packages, Modules, Sessions, and Tables – using the Authorization capabilities of the system.

In Baan IV, access can be given or denied on a user by user basis.

In Baan V and LN, the Authorization Management System can provide or deny access based upon roles to which users are assigned.

BPCS/LX Tip of the Week: Work Center - Cells

Anthony Etzel 0 60861 Article rating: No rating
The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.
First123124125126128130131132

Tips:  LX | BPCS | M3

Tips: LN | Baan

George Moroses

We're excited to unveil our revamped BPCS/LX Technical Staff Augmentation Services

We're excited to share some updates about our BPCS/LX Technical Staff Augmentation Services. At Crossroads, we're refining our staff augmentation structures to better cater to specific job descriptions. This enhanced offering is designed to provide our clients with the opportunity to seamlessly maintain product-level support (BPCS/LX – RPG) and development assistance. What sets this program apart is its ability to offer significant cost savings compared to traditional time and material arrangements. We aim to make staff augmentation more accessible and customizable to meet varying budgetary needs.

As part of this agreement, Crossroads will allocate a dedicated BPCS/LX technical resource for a set number of hours per week. The exact hours will be mutually agreed upon during the sourcing requirements discussions, ensuring that the support arrangement aligns perfectly with your needs.

Key Features of the Technical Staff Augmentation Service:

  • Flexible Hours: Tailored to your specific needs, we'll collaborate with you to determine a fixed number of hours per week that best aligns with your requirements.

  • Duration Options: Choose from flexible prepaid agreement durations of 3, 6, 9, or 12 months.

  • Remote Accessibility: Our technical services are primarily remote, but onsite assistance can also be discussed and arranged during the project kickoff phase, ensuring comprehensive support regardless of location.

  • Expertise Spectrum: Our dedicated BPCS/LX technical resources boast a comprehensive skill set, including proficiency in RPG, thorough documentation practices, design capabilities, familiarity with IBMi system foundations, job scheduling expertise, SQL proficiency, CL development capabilities, and more.

  • Scope Clarification: While our agreement primarily focuses on technical support and development assistance, application support falls outside the defined scope and can be considered separately upon request.

This innovative approach to technical staff augmentation is designed to streamline your operations, enhance system reliability, and empower your team to maximize the full potential of your BPCS/LX environment. Let's embark on this journey together, customizing technical staff augmentation solutions that precisely align with your business objectives and budgetary constraints.

Request a phone consultation or Learn More

Print
13412 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

x

Categories