Baan/LN Tip of the Week: Product Families

Kathy Barthelt 0 76474 Article rating: No rating

In Baan IVC, plan items on the lowest plan level were automatically actual items (not product families). All plan items on higher plan levels were product families.

The relationship between a product family and items on lower plan levels was defined in a planning bill of material.

In Infor LN, every family item must be defined in the Item Base Data module. A family item can exist on any plan level. The relationship between a family item and items on lower plan levels is defined in aggregation relationships.

Aggregation relationships in Infor LN are much more flexible than the planning bills of material in Baan IV. For example, users can define aggregation relationships between items on the same plan level.

BPCS/LX Tip of the Week: Create the Master Schedule

Anthony Etzel 0 78901 Article rating: No rating

In the master schedule creation, you have the flexibility to enter a planning start date, or default to the facility planning start date. Infor LX uses the planning date to plan both orders with forecasts and customer orders as demand.You can create your master schedule from the Master Production Scheduling module (MPS).

No one cares how hard you work! How you can do more, while doing less – know your MO.

David Dickson 0 56128 Article rating: 5.0

Would you like me to tell you a dirty, little secret?

No one cares how hard you work. Sure, some people will notice if you seem to be working hard. Your spouse or companion might note that you seem tired, stressed, not as much fun, or just aren’t around much, but they care about the consequences, not how hard you work. Your boss might note happily that his staff seems busy, things are humming along, but you can be sure that when it is review time she gets no credit for “keeps staff very busy.” Nor will the boss give you extra points for being busy. It is about results.

People outside your personal life, beyond your coworkers, might notice that you are hard to contact, perhaps because you are so busy. But trust me, customers do not care why they can’t get hold of you, and they will not see it as a positive.

Infor and Crossroads RMC are proud to offer a joint webinar on Taking Your Shop Floor Paperless - August 28th, 2014.

Anthony Etzel 0 45628 Article rating: No rating

Taking Your Shop Floor Paperless - Webinar, August 28th, 2014.

During this webinar, you will learn about the Crossroads MES Shop Floor Solution which gives you the ability to do all the following and more:

  • Collect production data
  • Provide real time feedback to your workers and your management team
  • Integrate to machines on your shop floor to pull counts directly
  • Provide up-to-date electronic versions of shop floor paperwork at the work center
  • Monitor your production against your key performance indicators
     

Join us on Thursday, August 28th at 12:00 p.m. Eastern to learn more.

TO REGISTER:

linked removed...

Baan/LN Tip of the Week: Company Calendar

Kathy Barthelt 0 74878 Article rating: No rating

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

BPCS/LX Tip of the Week: SFC600 & SFC650

Anthony Etzel 0 87172 Article rating: No rating

These programs are used to capture and post shop floor information. Labor reporting, machine time, etc. can be captured by either program. The key difference is that one will also capture the production receipt and backflush components. Based on your company information / transaction process, one of these programs will most likely be used daily to capture current shop floor data. You can use the shop packet labor ticket for the manual recording, and the keying of the data. Alternatively, you can incorporate an automated method like an MES solution to capture the data and streamline the process.

Crossroads RMC to Exhibit at Manufacturing Matchmaking 2014

Crossroads RMC 0 45200 Article rating: No rating
Crossroads RMC will exhibit at the inaugural Illinois Manufacturing Excellence Center (IMEC) Manufacturing Matchmaking Event 2014 on September 23, 2014. Manufacturers from across the state of Illinois will come together at this event to discuss ways to improve the productivity and competitiveness of Illinois' small and mid-sized manufacturing firms.

BPCS/LX Tip of the Week: What is the bubble number and how do I maintain it?

Anthony Etzel 0 79341 Article rating: No rating

The bubble number is maintained at the component level for each component defined on the Bill of Material. It is an extra user-defined reference number that you can use to re-sequence the maintenance screen display or bills of material listings.

In Infor LX, the system displays the bubble number for the existing child items. Engineering drawings often use a bubble number at the component level on the drawing so that same bubble number can be used on the Bill of Material for a link of the component to the drawing. Alternatively, you may use it simply as a method to sequence the BOM.

Be careful of how you assign the number. It is a good idea to assign the number with a consecutive count by 10 leaving room to allow for component additions to the Bill of Material.

First121122123124125127129130

Tips:  LX | BPCS | M3

Anthony Etzel
/ Categories: Infor LX & BPCS Tips

Infor LX & BPCS Tip of the Week: LX 8.4 Database

The database in LX 8.4 has undergone a significant change from previous versions. The database has been created using SQL DDL language instead of the old DDS language. The newer format allows for LX to take better advantage of advances in IBM database technologies as they move forward. Additionally, LX will be better able to make changes to tables (aka files) in the future without causing very large MR explosions to replace all programs that use a specific table. To ease the impact of this significant change, the LX tables (aka physical files) have new names that are the same as the previous version file names but with a “P” at the end, for example IIM is now IIMP. The old file names now belong to SQL views that looks just like the tables. This change made it easier to upgrade all the LX programs without changing every reference to every file. Many of the logical files remain although some have been replaced by SQL indexes to improve performance.
Previous Article Infor LX & BPCS Tip of the Week: Partial Search in Item Description List
Next Article Infor LX & BPCS Tip of the Week: ION Tip – Pausing Receiving and Sending of Messages
Print
57559 Rate this article:
5.0

Contact

Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

x

Tips: LN | Baan

Categories