BPCS/LX Tip of the Week: Top Down Shop Order Schedule

Anthony Etzel 0 76973 Article rating: No rating

In ERP LX, this function is called Backward Scheduling. This is a simple, easy way to create and release shop orders associated with the end item.

The result is a shop calendar with the associated order start dates. Setting up ERP LX properly with correct Queue Times, Setup and Run Times, along with Move Times, will result in accurate shop order start dates.

Baan/LN Tip of the Week: Back Dating Cycling Counting Orders

Kathy Barthelt 0 105054 Article rating: No rating

Cycle Count Orders cannot be directly “back dated” in Baan IV, Baan V or LN, however, there are some work-arounds.

In Baan IV you can do an inventory adjustment and back date. Just set all dates on the adjustment to the date you want and Baan will post the adjustment in that period.

In LN you can do a Cycle Count/ Adjustment and again back date and Baan will post to that period.

 

Unfortunately, there is no work-around for Baan V.

BPCS/LX Tip of the Day: Inventory Management

Anthony Etzel 0 74922 Article rating: No rating

Establishing the Quantity On-Hand and the Quantity Available.

LX maintains buckets for information associated with the following inventory transactions for each item:

  • Opening Balance
  • Issues
  • Receipts
  • Adjustments
  • Allocations for the Customer
  • Allocations for Manufacturing


The on hand quantity does not include any allocations. To arrive at the on hand quantity, start with the opening balance, less any issues, plus any receipts, then add or subtract any adjustments. Available inventory is the on-hand less any allocations.

 

 

Baan/LN Tip of the Day: Chart of Accounts

Kathy Barthelt 0 108407 Article rating: No rating

Zero sublevel accounts are posting level accounts. All others are parent accounts. Once the balances have been updated in the child ledger accounts, the parents are automatically updated.

Inquiries and reports can be printed or displayed either by child accounts or by parent accounts. On line drill-down is possible from either child or parent.

BPCS/LX Tip of the Day: Cycle Counting Part 2

Anthony Etzel 0 75985 Article rating: No rating

Understanding: The Cycle Count Alternative

The best way to cycle count is to count the same number of items each day and at the same time each day. The goal is to count your “A” items 4 times a year. The “A” items should be those item that are about 80% of the total inventory value and 20% of the total items. Consider creating your own cycle count schedule then instead of using the cycle count transaction, use the inventory adjustment transaction. The item balance is changed at the time the transaction is keyed. The transaction list can be used for the reconciliation process.

Baan/LN Tip of the Day: Company Calendar

Kathy Barthelt 0 104883 Article rating: 5.0

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning
    (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

BPCS/LX Tip of the Week: Cycle Counting Part 1

Anthony Etzel 0 82960 Article rating: No rating

Understanding: The Cycle Count Transaction

If you rely on BPCS to provide you with a cycle count list, the number of items could vary from day to day from a few items to count, to several. So the person doing the cycle counting may spend a few minutes to a few hours counting items. After the cycle count is complete, the balances are not changed until the reconciliation is complete. This process could take some time before the balances are changed.

The cycle count transaction process is similar to the physical inventory transaction process.

Baan/LN Tip of the Week: GRINYA

Kathy Barthelt 0 111052 Article rating: 3.0
GRINYA is one of the more complex issues in ERP Finance. GRINYA is the tracking via ledger account of the value of items received on a purchase order that have not been matched to a supplier invoice.

Baan solutions for Baan IV and V were incomplete. To take full advantage of the current GRINYA reconciliation process, check Infor solution #107147, which contains the GRINYA user manual and a link to download the software for your version of Baan. For ERP LN, look at Document Code U8942C US.

It is called User Guide for Reconciliation and Analysis. If you are not running the latest GRINYA solutions, patching will require a good amount of time in filling the Interim tables this solution runs from. Infor has posted several procedural write ups, so check the Support Site and read up before tackling this for the first time.
First120121122123125127128129Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Collaborate IN-PERSON With Infor LN Users

LN North America User Group - Face-to-Face 2022 (lnnaug.org)

Registration is open for the face-to-face LN North America User Group Annual Meeting!

Things are finally turning around and opening up! We're looking forward to the day when the pandemic stays firmly in the rearview mirror.

It's definitely exciting to be buttoning up the details of the agenda for this event. This is our chance to discuss successes and roadblocks with one another.

This is also an opportunity to spend time with the Infor team. We will have members of the Product Management and Product Development team in-house for presentations, discussion, and questions.

Catch this: Marco Hoogenraad & Bram Vijfhuizen are scheduled to join us on-site!

Seats are limited. Registration closes on April 8th or sooner if we hit that limit.

Don't miss out, register today! We are looking forward to seeing everyone again and hope to see YOU there!

Curious about the agenda? Find it here: https://www.lnnaug.org/events-underway/agenda

Catch the details:

When: 2 full days | April 19 & 20, 2022

Sponsored dinners: April 18 & 19

Registration fee: To attend this event, there is NO COST to customers other than arranging and covering their own travel & lodging at a hotel in Columbus, Ohio.

Registration: Registration is open!

Agenda: The agenda will be a mix of learning sessions, customer stories, discussion groups, and networking time. If you have any questions shoot us an email at lnbaan.naug@gmail.com.

Travel Information

Where: Columbus, Ohio | Brookshire: The Venue at 405 Greif Pkwy, Delaware, OH 43015

Airport Code: CMH - a 20-minute drive from this airport to local hotels. 10 minutes from the hotel to the event location.

Hotels
Cambria Hotel Columbus - Polaris | 9100 Lyra Drive, Columbus, OH, 43240, US | Phone (614) 841-9100 Fax (614) 841-9107
Hilton Garden Inn | 8535 Lyra Dr, Columbus, OH 43240 | Phone: (614) 846-8884
Other hotels that are in Polaris, Columbus, OH would work fine as well.

Print
25268 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories