Baan/LN Tip of the Week: Old Porting Set

Kathy Barthelt 0 54293 Article rating: No rating

Here are some issues that you might run into if you stay on an old porting set too long:

  • Incompatibility because of operating system patches
  • Printing issues because of out-of-date libraries
  • Potential performance issues if binaries are not updated
  • Updating third-party products may not be possible because of dependencies
  • Limited support from Infor
  • Issues with updating database software/patches because of dependencies (if the database is also running on the same server as the application)

Need help getting on a newer porting set? Let us know! We’d be happy to help.

Crossroads MES Released for Windows 10

Anthony Etzel 0 28747 Article rating: No rating

Crossroads RMC is pleased to announce the availability of Crossroads MES, V11 for Windows 10. Any customers wishing to upgrade from a previous version to V11 can do so by contacting  support@crossroadsrmc.com. As previously announced, Crossroads MES  is also compatible with tablet PCs running Windows 8.1. Tablet PCs are becoming the clipboard replacement for supervisors and managers to monitor what’s happening on the shop floor.

BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 65237 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 62054 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

BPCS/LX Tip of the Week: Receiving to Inspection

Anthony Etzel 0 69373 Article rating: No rating

If the item being received needs to be inspected prior to being available for use, there are two schools of thought.

The first is to receive the item to a QC hold location. The downside is the item will show up in on hand inventory.

A better method would be to do a PO receipt to inspection. Both Inv500 and Pur550 support this method. Now you have received the item without showing it in inventory. Only the PO quantity in inspection is updated. This method also allows you to create an Inspection Dispatch Report. After the QC process for the item is complete, then the transaction Receipt from Inspection to Stock is processed. That transaction then updates the PO quantity received field and the Item on hand field in inventory.

Baan/LN Tip of the Week: Purchase Inquiry

Kathy Barthelt 0 88226 Article rating: No rating

In Baan IV Purchase Control, the purchase inquiry procedure enables the user to:

  • Request a specific supplier to submit a quotation on the purchase inquiry for the delivery of an item.
  • Compare the prices and discounts of the quotations that are submitted by different suppliers.
  • Copy the inquiry data to a purchase order.


In LN, you can:

  • Request multiple business partners to submit a quotation on a specific request-for-quotation for the delivery of an item.
  • Compare the received quotations based on the following criteria:
  1. Price
  2. Quantity
  3. Vendor rating
  4. Delivery dates
  5. RFQ subjective criteria
  • Copy the quotation data to a purchase order, a purchase contract, or a price book.

BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 61342 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 63969 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

First118119120121123125126127Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Crossroads RMC

5 WARNING SIGNS Your Disconnected Business Systems Are Costing You Money

  1. You Can’t Track Project Costs in Real-Time
    If you're waiting until after a project wraps up to find out whether it was profitable, that’s a major red flag. Without real-time cost tracking, you're making critical decisions in the dark.

  2. Quoting and Estimating Are Slow, Manual, or Inconsistent
    Does it take hours—or even days—to build a custom quote because you're pulling information from multiple systems? That lost time translates directly into lost sales opportunities.

  3. You Rely on Spreadsheets for Critical Operations
    Spreadsheets are useful—until they’re not. Issues like version control problems, accidental overwrites, and human error can lead to costly mistakes.

  4. Scheduling and Inventory Management Are Disconnected from Financials
    If your production and finance teams aren’t working from the same data, it’s only a matter of time before you face delays, stockouts, or budget overruns.

  5. You Don’t Have a Real-Time View of Project Profitability
    Without live costing tied directly to jobs, small losses can accumulate unnoticed, until it's too late.

Disconnected data refers to information stored outside your core business systems, like your ERP. While this data has value, a lack of integration causes inefficiencies and misalignment across your organization, often more than you realize.


The Cost of Disconnected Data

In a recent study by SnapLogic and Vanson Bourne, 500 business users and IT decision-makers in large enterprises across the US and UK were surveyed. The findings reveal the true cost and challenges of disconnected data:

  • $140 billion is lost annually due to wasted time, duplicated efforts, and missed opportunities.

  • 47% say disconnected data negatively affects their ability to innovate and bring new products/services to market.

  • 46% report it impairs their ability to engage and support customers effectively.

  • 56% believe data silos are creating barriers to achieving business goals.


How Crossroads RMC Can Help

At Crossroads RMC, we specialize in integrating disconnected systems and data into your ERP environment. Our expert consultants, with decades of experience, help you:

  • Eliminate redundant data entry

  • Enhance operational efficiency

  • Enable real-time updates to and from your ERP

  • Gain a unified view of your business for better, faster decision-making


Our Integration Services Include:

Let Crossroads RMC help you connect disconnected systems into a unified enterprise.

Contact Us   |  800.762.2077

Print
7842 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

x

Categories