Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 1943 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

BPCS/LX Tip of the Day: Cost Accounting – LX

Anthony Etzel 0 868 Article rating: No rating

The challenge in cost accounting is tracking your manufacturing to the levels needed for useful management information. You need feedback for corrective action; but, you need to minimize the cost of collection. Some parts of your operation require specific job-cost tracking while the Just-in-Time areas require

costing in terms of cost per process hour or day. Apply overhead in different ways to different processes and products. Segregate costs into enough detail

to provide management with an accurate picture of the contents of your product. Material, material overhead, labor, fixed overhead, variable overhead, outside processing, outside processing overhead, and so forth all have to be considered.

 

LX meets your cost accounting needs with the following functionality:

▪ Four sets of costs: actual, standard, frozen standard, and simulated

▪ Nine user-defined elements per set

▪ Full and partial cost roll-up and simulation

▪ Cumulative in-process cost tracking

▪ Cost summaries by item

▪ Cost definition tied to work centers or material type

▪ Process hour costing

Baan/LN Tip of the Day: Vendor Rating

Kathy Barthelt 0 1416 Article rating: No rating

In LN, a supplier's reliability is no longer based only on correct deliveries. The vendor rating functionality of LN is based on various objective criteria and subjective criteria that can be used to calculate the vendor’s rating.

 

The set up procedure for analyzing suppliers has changed completely compared to Baan IV.  To execute the vendor rating process, users must update the vendor ratings in the Update Vendor Rating (tdpur8850m000) session.

If users update the vendor ratings, the following stages exist in the update vendor rating procedure:


1. Calculate actual weightings

2. Calculate ratings for objective criteria

3. Calculate ratings for subjective criteria

4. Update overall vendor rating

Baan/LN Tip of the Day: Release Commissions/Rebates to Invoicing

Kathy Barthelt 0 3103 Article rating: No rating

In Baan IV, this session is called Release Commissions/Rebates to Invoicing (tdcms2201m000) and is used to set the status of the commissions/rebates to Reserved, or Closed. In Infor LN, this session is only used to set the status to  Closed. Users can reserve commissions/rebates in the Reservation and Approval of Reserved Commissions/Rebates (tdcms2202m000) session. In addition, the following fields are added to the Release Commissions/Rebates to Invoicing (tdcms2201m000) session:

▪ Commissions to Accounts Payable

▪ Rebates to Central Invoicing

BPCS/LX Tip of the Day: How Does LX Fit in With Just-In-Time?

Anthony Etzel 0 364 Article rating: No rating

For years, repetitive manufacturing industries have been applying many of the principles in Just-in-Time philosophy. They have established balanced production lines that depend on a steady flow of material to each work station. They schedule production in daily or weekly rates rather than in discrete shop order lots. They track finished inventory by work center rather than by job. They typically backflush stock balances (decrement stock balances upon completion of specific manufacturing steps rather than issued at the beginning of each production run).

 

Costing is typically based upon a daily rate or hourly rate rather than being associated with specific shop orders. 

 

Repetitive manufacturers use MRP II software adaptable to their environments

in the following key areas:


 Product definition

 Inventory tracking

 MRP/Master Scheduling

 Shop Floor Control

 Purchasing

 Costing

BPCS/LX Tip of the Day: What is Just-In-Time?

Anthony Etzel 0 313 Article rating: No rating

Just-in-Time (JIT) is a management philosophy that focuses on minimizing the resources necessary to add value to your products and to operate your factory in ways that eliminate waste. Resources are labor, materials, equipment, space, and time. Waste is anything that does not add value to your products. Moving work-in-process from place to place, stacking and sorting, investing capital in large work-in-process and raw material inventories, inspecting materials at your vendors' sites, and tying up warehouse space with finished goods are all activities that add cost, not value, to your products. 

JIT is a process that reduces lead time. JIT does not replace an MRP, an inventory program, a scheduling technique to bypass your Master Schedule, or a materials management project. JIT is the never-ending commitment of everyone, from top management to your workers on the floor, to maximize your effectiveness through continuous, incremental improvements.

Baan/LN Tip of the Day: Configuring Items

Kathy Barthelt 0 2237 Article rating: No rating

In LN, the configuration of a generic item not always results into a customized item. Configured items can now be customized items as well as standard items. If users configure items without PCS projects, standard items are generated instead of customized items.

 

The sessions for generating product variant structures for sales quotations and sales orders are moved from the Product Configuration module in Manufacturing to the Sales Control module in LN. The following new sessions are available in Sales Control:

▪ Generate (Budget) Structure for Sales Quotations (tdsls1201m100).

▪ Generate (Project) Structure for Sales Orders (tdsls4244m000)

BPCS/LX Tip of the Day: Shop Order Control

Anthony Etzel 0 443 Article rating: No rating

To create and maintain shop orders use SFC500 Shop Order Entry Maintenance. These orders use the standard bill of material (BOM) as the base list of components. You can also set up standard routings, which list the operations,

or work steps, involved in manufacturing.

 

To release shop orders, use the Shop Order Release program, SFC505. Infor ERP LX groups shop orders by user ID for batch processing. Use Shop Packet Print, SFC520, to print the shop orders that you select. SFC530 allows you to create multi-level shop orders to link shop orders together with a common end item parent. Linking multiple shop orders together for a final assembly product provides support for make-to-order and engineer-to-order manufacturing environments which need to schedule these multiple orders together or as a vertical slice in the production schedule.

 

You can make changes to shop orders after you print them. Use Shop Order Entry/Maintenance, SFC500, to update the shop orders. Changes are immediately visible on the inquiry screens for SFC300 and SFC350. To reprint the shop packet, use Reprint Shop Packet, SFC560.

First110111112113115117118119Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Digital Transformation & Your ERP

70% of global executives said the pandemic will accelerate their digital transformation pace

Transformation: (definition)  A thorough and dramatic change.

We all dream about it….how can we transform ourselves into something better…something more desirable? Maybe it is our appearance that we want to improve, maybe it is our physical strength and stamina, or maybe it is our mental toughness.

Have we thought about transformation when it comes to our businesses? More specifically, our ERP systems that are the lifeblood of our businesses?

When it comes to this type of transformation, we’re talking about a digital transformation. This means taking disconnected business systems and manual processes and transforming or converting those systems into a world where achieving greater efficiencies, collaboration, improved delivery speed, and greater customer satisfaction is not only possible but probable.

As the world becomes more digital, so must organizations large and small, despite the unexpected. One survey found that 70% of global executives said that the pandemic will inevitably accelerate their digital transformation pace. https://dmexco.com/stories/is-the-coronavirus-pandemic-an-engine-for-the-digital-transformation/

ERP has a major impact on digital transformation. When it comes to ERP, transformations are often referred to as ERP Modernization. Here is just a sampling of how ERP modernization can impact your business:

  • Cost Reduction – Supporting legacy software and on-premise servers requires resources, but not just any resources. You must have resources that know the ins and outs of software and hardware that is decades old. Older software and platforms often result in higher maintenance costs and significant limitations to overall data management and system performance. Moving to the cloud, or the latest version of on-premise systems opens many doors that would otherwise be closed to you.
  • Eliminating Data Silos – Separate databases and disconnected systems mean that collaboration and communication are not possible. Missed opportunities abound for increased productivity. What would it mean to your business for all personnel to be operating off the same set of data and getting updates in real-time?
  • One Cohesive System –  Using ERP add-ons is helpful, but unless the systems talk to one another, duplicate data entry is required and real-time updates aren’t possible. How can you truly take advantage of the investment you made in a CRM or inventory management system if it doesn’t communicate with your ERP?
  • Visibility Across the Supply Chain –  No idea when your supplier is going to deliver the parts you need? Are you literally calling or waiting for an email to be sent? If that is how you’re getting updates, you’re likely not getting them timely enough to properly respond to those updates. Customer satisfaction issues can greatly be eliminated with real-time updates and complete visibility up and down the supply chain. With global supply chain issues prevalent in most industry sectors, visibility becomes more important than ever.
  • Scalability Becomes Possible – When your business needs change, your ERP system should be capable of handling the growth or increased functionality requirements to support it. This can be achieved by staying current on the ERP version or at least getting to a version where integrations with complementary systems are possible.

Transformations don’t happen with one act or one giant step. They happen with small steps and interim goals that can and should be celebrated along the way. Need help deciding when or where that first step should take place? Need someone to be your coach for the transformation? Contact Crossroads RMC today for recommendations, best practices, and solutions for this all-important journey for your business. 

800.762.2077 or click here to get a free phone consultation!

Print
20363 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

x

Categories