Infor LX / BPCS Tips & Tricks for Operations: Retain Lot Status on Shipped Resupply Orders

George Moroses 0 13783 Article rating: 5.0

When a lot is completely shipped on a customer order, the Lot Status is changed to Z. Since a resupply order must still be received in the To Warehouse to complete the transaction, do not update the lot status when the resupply order is shipped. If a lot is completely shipped on a resupply order, LX no longer updates the lot status to Z, because the shipped lot retains its current lot status, the additional steps, no additional steps are required to receive it in the To Warehouse.

Infor LX / BPCS Tips & Tricks for Technology: Reset Purchase Order In Use

George Moroses 0 14588 Article rating: 5.0

This feature resolves or resets a purchase order or requisition that is no longer being processed, but the system still indicates it is 'in use'. The user selects Purchase Order/Requisition in Use Maintenance, PUR940D, from the Purchasing Management Menu, PUR, located in the Special Processing sub-menu. The user then enters an order or requisition to remove the 'In Use' status.

End of Year E R P Checklist: Streamline Your Transition to the New Year

Crossroads RMC 0 7352 Article rating: 5.0

The end of the year is a busy time for everyone, but a little preparation can make the start of the next year smoother and more productive. Here's a checklist broken out by the department to help optimize your ERP system as you wrap up this year.

  1. All Departments Checklist
  2. Technology Checklist
  3. Operations Checklist
  4. Finance Checklist

Infor LN & Baan Tips & Tricks: Action Required - Infor LN Cloud Edition - Fonts Update!

Kathy Barthelt 0 62318 Article rating: 5.0

In April 2025, Infor LN Cloud Edition release 2025.04 will introduce the deprecation of Windows® fonts in LN report design and output. This means that Windows fonts will need to be replaced by Google fonts.

Actions Required:

  • All LN Cloud Edition customers must identify all reports modified with the LN report designer and update them by replacing the Windows fonts with Google fonts.
  • Completed before the 2025.04 Maintenance Window.
  • Please see Knowledge Base (KB) article 3523663 for more information, details and FAQs.
First678911131415Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

George Moroses
/ Categories: Infor LX & BPCS Tips

Infor LX & BPCS Tip: Capacity Planning – Resource Requirements Reports

Resource Requirements Report (CAP260D) generates five capacity reports:

  • Labor Resource Requirements
  • Machine Resource Requirements
  • Setup Resource Requirements
  • Setup and Labor Requirements
  • Setup and Machine Requirements

The Labor Resource Requirement report lists requirements that are calculated from the run hours on each routing and the MRP/MPS demand in the Capacity Requirements Detail File (LCR). The calculation does not consider crew size.

The Machine Resource Requirement report lists machine hour requirements based on routings and the MRP/MPS demand in the Capacity Requirements Detail File (LCR).

The Setup Resource Requirements report lists setup labor requirements based on routings and the MRP/MPS demand in the Capacity Requirements Detail File (LCR).

The last two reports combine setup hours with labor hours and setup hours with machine hours to provide two separate reports that summarize the requirements by work center with totals by department. The system computes requirements similarly to the way it computes them on the other reports.

Have questions on this process or need some help? Contact us! Our experienced consultants will be glad to assist you.