Hoffmaster Clintonville Plant Goes Live with Crossroads MES & LX

Anthony Etzel 0 32461 Article rating: No rating

On March 1, 2016, Hoffmaster’s Clintonville plant went live with Crossroads MES and LX. The goal of the project was to convert from another ERP to LX and replace a green screen MES system that required the manual recording of production and labor activity keyed from shop floor terminals.

Hoffmaster achieved their goal by completing a successful data conversion and detailed prototyping of LX and Crossroads. The project team remarked that the Crossroads MES implementation was by far the easiest part of the project. One of the critical requirements of the chosen MES solution was to verify UPC and UCC label formats that called for in-line labeling of product packages and cases. Crossroads MES satisfied that requirement, and also provided an interface to finished goods inventory via the scanning of LPN numbers when reporting production.

The Clintonville plant is a leading manufacturer of disposable tabletop products.

BPCS/LX Tip of the Week: Actual Costs for Manufactured Items

Anthony Etzel 0 52682 Article rating: 5.0

In LX, the actual costs that can be set up fall into three categories: Material, Labor, and Overhead. If your LX database is set up properly with the LX cost accounting, you should be able to identify:

  • How much the item should cost
  • How to track the cost of work underway
  • How much the item actually did cost
  • Why the job cost varied from the expected cost
     

Capturing the data to track activity with associated costs can be time-consuming. With an MES solution, the information you need for costing is tracked instantly.

Baan/LN Tip of the Week:GRINYA Reconciliation – What Could Go Wrong?

Kathy Barthelt 0 77192 Article rating: No rating

One common GRINYA issue would be incorrectly entered Integration Setups.

Check the Baan or LN manual for recommended Integration setups. If such a mistake were to occur, it is important to know for what period of time the Integration was in error.

To ensure, it’s recommended that the Integrations Setup tables should be audited either through Baan/LN or Database Auditing. Corrections can be quickly calculated when an exact timeframe can be determined.

Morrison Brothers Goes Live With Crossroads MES in Record Time!

Crossroads RMC 0 31541 Article rating: No rating

On February 18, 2016, the Maquoketa plant of Morrison Brothers went live with the Crossroads MES solution. The goal was to remove all the shop floor paperwork and eliminate the manual recording of production and labor. The company achieved this goal in just 96 days from project kick-off to go live. Included in the go-live was the ability to deliver drawings electronically to the Crossroads MES workstations. This was a critical component of the implementation as it ensured that each workstation would always be operating off the latest revision of the engineering documents.

A rollout of the Crossroads MES solution is planned for Morrison’s Dubuque plants later this year. 

Morrison Brothers is a major producer of petroleum marketing equipment in the United States and abroad.

Baan/LN Tip of the Week: Old Porting Set

Kathy Barthelt 0 72888 Article rating: No rating

Here are some issues that you might run into if you stay on an old porting set too long:

  • Incompatibility because of operating system patches
  • Printing issues because of out-of-date libraries
  • Potential performance issues if binaries are not updated
  • Updating third-party products may not be possible because of dependencies
  • Limited support from Infor
  • Issues with updating database software/patches because of dependencies (if the database is also running on the same server as the application)

Need help getting on a newer porting set? Let us know! We’d be happy to help.

BPCS/LX Tip of the Week: Establish Costing For Purchased Items

Anthony Etzel 0 51071 Article rating: No rating

How Does Infor LX Establish Costing For Purchased Items?

In LX, you will establish a standard cost (you define the standard) that LX will use for the purchase items. You also need to establish in LX the Cost Type, the Cost Bucket, and the Cost Set needed for cost accounting.

Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 84162 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Crossroads RMC Releases NextTrack Sales – Sales Analysis Tool for Baan, Infor LN and IBM i

Kathy Barthelt 0 32670 Article rating: No rating

Crossroads RMC is proud to announce the official release of NextTrack Sales – a sales analysis tool for Baan, LN, and IBM i. NextTrack Sales allows you to get the “big picture”, or get down into the finer details. The tool provides a sophisticated pivot grid and charting functionality, export to Excel, PDF printing, and emailing capabilities to bring your sales data to life. Analyze your Baan Sales data to examine trends, identify market opportunities, and much more. Click here for more details.

First103104105106108110111112Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

[EasyDNNnews:IfExists:Event]
[EasyDNNnews:IfExists:EventRegistration][EasyDNNnews:EventRegistration:RegisterButton][EasyDNNnews:EndIf:EventRegistration] [EasyDNNnews:IfExists:Payment][EasyDNNnews:Price][EasyDNNnews:EndIf:Payment] [EasyDNNnewsLocalizedText:Eventdate]: [EasyDNNnews:EventDate] [EasyDNNnewsLocalizedText:ExportEvent] [EasyDNNnews:IfExists:EventLocation]

[EasyDNNnewsLocalizedText:EventLocation]: [EasyDNNnews:EventLocation]

[EasyDNNnews:EndIf:EventLocation] [EasyDNNnews:IfExists:EventRegistration]
  • [EasyDNNnewsLocalizedText:NumberOfAttendants]: [EasyDNNnews:EventRegistration:NumberOfAttendants]
  • [EasyDNNnewsLocalizedText:MaxNumberOfTickets]: [EasyDNNnews:EventRegistration:MaxNumberOfTickets]
  • [EasyDNNnewsLocalizedText:NotUsedTickets]: [EasyDNNnews:EventRegistration:NotUsedTickets]
  • [EasyDNNnews:IfExists:Payment]
  • [EasyDNNnewsLocalizedText:Price]: [EasyDNNnews:Price]
  • [EasyDNNnews:EndIf:Payment]
[EasyDNNnews:EventRegistration:InfoMessage] [EasyDNNnews:EndIf:EventRegistration] [EasyDNNnews:IfExists:EventSignUp]

[EasyDNNnewsLocalizedText:AreYouGoing]

[EasyDNNnews:SignUpActionBar]
[EasyDNNnews:EndIf:EventSignUp]
[EasyDNNnews:EndIf:Event]
Kathy Barthelt
/ [EasyDNNnewsLocalizedText:Categories]: [EasyDNNnews:Categories]

Infor LN & Baan Tips & Tricks for EXECUTIVES

OPERATIONS: Update, Cancel or Remove Outbound Order Lines
When the originating order or order line of an outbound order line is canceled or changed, this affects the outbound order line and may affect the related outbound advice, shipments, or shipment lines.

For most order origins, warehousing order-type parameters determine whether these actions are allowed:

  • Update the outbound order line if the originating order is changed.
  • Cancel the originating order line and the outbound order line.
  • Delete the canceled outbound order line.

If updating is allowed, changes made to the originating order are updated to the outbound order line and the related outbound advice, and, if present, picking lists, are deleted.

If updating is not allowed, a message is displayed, and the input is blocked when you try to change the originating order line.

If canceling is allowed, the outbound order line is deleted or set to Canceled when the originating order line is canceled.

When a canceled outbound order line is deleted, if present, the related outbound advice and picking list are also deleted. Outbound order lines originating from manual order origins cannot be deleted when canceled.

To process an outbound order line that is not deleted but set to Canceled, the outbound order line must be set to Shipped. The status of the outbound order line determines whether all steps of the outbound and shipment procedures must be completed to process the outbound order line.

When a canceled outbound order line is set to Shipped, the shipped quantity is automatically set to 0. You can create a transfer order to return the not-shipped goods to inventory.

If canceling is not allowed, you cannot cancel the originating order line or the outbound order line. A message to that effect is displayed when you try to cancel the originating order line.

To prevent the goods from being shipped when canceling is not allowed, you must complete the outbound and shipment procedures. When confirming the shipment line, you must set the shipped quantities to 0 and create a transfer order to return the not-shipped goods to inventory.

FINANCE: Currency Differences Accounts
Currency differences can make the financial analysis and reconciliation more complex. These types of currency differences can occur:

  • Currency differences
    Currency result caused by fluctuations in the exchange rate, for example, if the rate differs between the invoice date and the payment date.

  • Exchange gain and loss
    Currency result caused by the use of different exchange rate types, for example, the Sales rate type and the Internal rate type, or if using the rate determiner you have changed the exchange rate for a transaction during the order handling procedure.

  • Translation gain and loss
    Currency result caused by the use of different currencies during the order handling procedure, for example, if the order currency or the payment currency differs from the invoice currency.

  • Destination gain and loss
    Currency result caused by different results when the transaction currency is converted to the various home currencies. Destination gain and loss can only occur in an independent currency system.

To support good reconciliation possibilities, currency differences and exchange gain and loss are posted to these accounts:

  • Exchange Gain and Loss
    For differences between related amounts (debit and credit postings) due to different exchange rate types or different currency rates.

  • Currency Translation
    For transactions in which the debit posting and the credit posting are made in different currencies.

  • Currency Differences contra account
    For currency differences on the invoice accrual account due to rate changes between the receipt date and the approval date of the invoice and calculated when you close a financial period.


TECHNOLOGY: Advantages of Data Replication
Instead of sharing tables through logical linking, you can replicate table content between companies. This approach allows certain non-key attributes of a record to vary by company. For example, if you replicate bills of materials rather than sharing them, each company can associate a different warehouse with the same bill of material. This way, the bills of materials are consistent across companies, while the warehouses can differ.

Replication also enables selective availability of records in other companies. For instance, when replicating items, you might limit which items are available in a sales company based on their item group, only including end items. You can further refine replication to specific subsets, such as particular item groups.

Keep in mind that replication requires any referenced tables to be either replicated or shared as well.

Previous Article Infor LN & Baan Tips & Tricks for TECHNOLOGY: Advantages of Data Replication
Next Article Infor LN & Baan Tips & Tricks for FINANCE: Use of Electronic Bank Statements
Print
55874 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories