Infor LX & BPCS Manufacturing Tip: Shop Calendar Maintenance – SFC140D1

Shop calendar maintenance, SFC140D1 This program features multiple-level shop calendar maintenance. You can maintain a shop calendar at the global, facility, or work center level. Global level entries override default values found in Work Center Maintenance, CAP100D1, for any program that uses the shop calendar.

Facility overrides affect all work centers in a Facility and are exceptions to the global level. Exceptions defined at the Facility level apply to all work centers for the facility. Work Center calendar entries are the most specific. These entries apply to a single work center and override any Global or Facility conditions.

If you have deleted a work center in Work Center Maintenance, CAP100D1, you cannot delete its shop calendar. The system treats the work center shop calendar like a global calendar for that year. If you try to delete it, you will delete the global shop calendar for that year.

Range processing provides daily or weekly maintenance of all overrides for a period of up to one year with a single command.

The following explains how Infor LX uses calendars for manufactured and purchased parts planning:

  • Infor LX treats purchased and manufactured parts in the same way.
  • Infor LX does not use the work center calendar.
  • In facility planning, Infor LX uses the facility calendar.
  • If the global calendar has additional days blocked out relative to the facility calendar, MRP/MPS plans consider both the facility and global days-off.


In all cases, the system uses the item master/CIC lead time parameter to determine the release date for the planned order regarding the due date from the forecast or parent demand. The system considers days blocked out in the facility and global calendars when it determines the planned order release date.

Example: Assume the entire system (Global) has a specific date set as a regular workday. If one particular Facility recognizes this day as a holiday, no hours are available on work centers within that facility. If conditions at one work center are an exception to this holiday, that work center can be maintained with its own set of conditions.

Simulation Mode

The Shop Calendar Selection/Maintenance Simulation program, MRP747B, uses the Shop Calendar Maintenance programs, SFC140D, in a simulation mode. The MRP program allows you to maintain shop calendar information to simulate capacity planning and to view the results before you use the data in live capacity planning.

When you run MPS by facility, you cannot maintain global calendars. This safeguard prevents a user from unintentionally overwriting the live global calendar if the user runs Copy to Live, MRP770D.

Access: Menu SFC

Previous Article Infor LX & BPCS Materials Tip: Over-Receipts
Next Article Infor LN & Baan Manufacturing Tip: Performance Problems in Generate Order Planning (cprrp1210m000)
Print
26434 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

To utilize the Security Rules Optimization feature, a system administrator can assign security codes to 100 pre-defined user groups. User groups are created in the Group Security Maintenance (SYS603) program. All users assigned to this group possess the same level of security.   

A system administrator can assign security codes for up to 100 of the user groups. All user groups over 100 are still administered by all security reject/allow rules assigned to them but are not able to utilize the optimized process. 

Each of the security codes and access levels are assigned to user groups and are mapped to the account strings and stored in the Account Cross Reference (CEA106D1) file.   

Once security codes have been assigned, the system administrator must: 

  • Determine which level each group is allowed access.

  • Determine which segment values/account strings are assigned to which user groups.

  • Create security rules for specific segment values/account strings and assign these groups to the created rules.

  • Select the rules to be processed.  Processing can be done in either batch mode or interactively.

  • The Security Rules flag must be on in the CEA Control Parameters program before any rules are effective. 

This feature provides a parameter that allows the user to enter expiration dates on the Inventory Transaction Posting screen, INV500, and Purchase Order Receipts screen, PUR5505, when they have received a lot controlled item that is not QMS controlled. This new field allows an expiration date to be entered and not overridden. A system parameter was added to Advanced Process Industries Parameters, API820D. When the parameter is set to Yes, a new lot expiration date is available in the Inventory Transaction Posting, INV500D2, and Purchase Order Receipts, PUR550D2, screens.