Infor LX & BPCS Manufacturing Tip: Shop Calendar Maintenance – SFC140D1

Shop calendar maintenance, SFC140D1 This program features multiple-level shop calendar maintenance. You can maintain a shop calendar at the global, facility, or work center level. Global level entries override default values found in Work Center Maintenance, CAP100D1, for any program that uses the shop calendar.

Facility overrides affect all work centers in a Facility and are exceptions to the global level. Exceptions defined at the Facility level apply to all work centers for the facility. Work Center calendar entries are the most specific. These entries apply to a single work center and override any Global or Facility conditions.

If you have deleted a work center in Work Center Maintenance, CAP100D1, you cannot delete its shop calendar. The system treats the work center shop calendar like a global calendar for that year. If you try to delete it, you will delete the global shop calendar for that year.

Range processing provides daily or weekly maintenance of all overrides for a period of up to one year with a single command.

The following explains how Infor LX uses calendars for manufactured and purchased parts planning:

  • Infor LX treats purchased and manufactured parts in the same way.
  • Infor LX does not use the work center calendar.
  • In facility planning, Infor LX uses the facility calendar.
  • If the global calendar has additional days blocked out relative to the facility calendar, MRP/MPS plans consider both the facility and global days-off.


In all cases, the system uses the item master/CIC lead time parameter to determine the release date for the planned order regarding the due date from the forecast or parent demand. The system considers days blocked out in the facility and global calendars when it determines the planned order release date.

Example: Assume the entire system (Global) has a specific date set as a regular workday. If one particular Facility recognizes this day as a holiday, no hours are available on work centers within that facility. If conditions at one work center are an exception to this holiday, that work center can be maintained with its own set of conditions.

Simulation Mode

The Shop Calendar Selection/Maintenance Simulation program, MRP747B, uses the Shop Calendar Maintenance programs, SFC140D, in a simulation mode. The MRP program allows you to maintain shop calendar information to simulate capacity planning and to view the results before you use the data in live capacity planning.

When you run MPS by facility, you cannot maintain global calendars. This safeguard prevents a user from unintentionally overwriting the live global calendar if the user runs Copy to Live, MRP770D.

Access: Menu SFC

Previous Article Infor LX & BPCS Materials Tip: Over-Receipts
Next Article Infor LN & Baan Manufacturing Tip: Performance Problems in Generate Order Planning (cprrp1210m000)
Print
26431 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In light of the recent tariffs on imports from Canada, Mexico, and China, effective April 2, 2025, adapting your business operations is crucial to your success. Infor ERP LX offers robust solutions for managing these new trade regulations through its advanced tariff processing functionalities. This system ensures accurate duty calculations and compliance with the latest regulations, helping you streamline operations and maintain competitiveness.

For specialized support and to optimize your ERP system, partner with Crossroads RMC. Our expertise in ERP LX will help you navigate these changes efficiently.

Learn how Infor ERP LX and Crossroads RMC can support your business in these evolving times.

You can create new macros in the Infor LX Configurable Enterprise Financials CEA107. 

On the Macro Definition window, you define the source file and the field in which you perform an arithmetic or special operation. For example, you can create a macro to accrue sales commission based on revenue. Your source file and field are the Invoice Line History (SIL) file and the G/L revenue (ILREV) field. 

Select Functions to access the Macro Functions window, on which you define the arithmetic, character, or special operation to process against the defined source field. In the previous example of accrued sales commission, you enter an arithmetic operation of multiply (*) and an operand value for the percentage, such as 0.05 for five percent. 

Note:  Previously created user defined macros will have to be updated to include any expanded field sizes in V84. 

FirstLast

Tips: LN | Baan

Categories