Infor LX & BPCS Tip: What items should be M-P-S planned vs. M-R-P planned?

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.

Previous Article Infor LN & Baan Tip: Separate item codes for incoming & outgoing subassemblies
Next Article Infor LN & Baan Finance Tip: Unallocated Payment
Print
33788 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

To utilize the Security Rules Optimization feature, a system administrator can assign security codes to 100 pre-defined user groups. User groups are created in the Group Security Maintenance (SYS603) program. All users assigned to this group possess the same level of security.   

A system administrator can assign security codes for up to 100 of the user groups. All user groups over 100 are still administered by all security reject/allow rules assigned to them but are not able to utilize the optimized process. 

Each of the security codes and access levels are assigned to user groups and are mapped to the account strings and stored in the Account Cross Reference (CEA106D1) file.   

Once security codes have been assigned, the system administrator must: 

  • Determine which level each group is allowed access.

  • Determine which segment values/account strings are assigned to which user groups.

  • Create security rules for specific segment values/account strings and assign these groups to the created rules.

  • Select the rules to be processed.  Processing can be done in either batch mode or interactively.

  • The Security Rules flag must be on in the CEA Control Parameters program before any rules are effective. 

This feature provides a parameter that allows the user to enter expiration dates on the Inventory Transaction Posting screen, INV500, and Purchase Order Receipts screen, PUR5505, when they have received a lot controlled item that is not QMS controlled. This new field allows an expiration date to be entered and not overridden. A system parameter was added to Advanced Process Industries Parameters, API820D. When the parameter is set to Yes, a new lot expiration date is available in the Inventory Transaction Posting, INV500D2, and Purchase Order Receipts, PUR550D2, screens.

FirstLast

Tips: LN | Baan

Categories