Infor LN & Baan Tips & Tricks for OPERATIONS: Creating a Purchase Order with Subcontracting

To create a purchase order (with subcontracting) third party outsourcing from purchase order, execute these steps:

  1. Create a purchase order using the same data set defined in the Subcontracting Models (tisub1100m000) session.
  2. In the Purchase Order Intake Workbench (tdpur4601m200) session, click New. The Purchase Order (tdpur4100m900) session is displayed.
  3. Select the business partner in the Business Partner field, Press Tab. Note: Infor LN populates the default data for the selected business partner in the other fields of the purchase order header.
  4. Select the order type for subcontracting in the Order Type field, purchase office in the Purchase Office field, and the related order series in the Order field.
  5. Click New on the Order Lines tab and select your subcontracted price item in the second segment of the Item field.
  6. Specify the required quantity in the Ordered Quantity field, price of the item in the Price field and click Save.
  7. Click the Approve button to approve the purchase order. The purchase order Status is updated to Approved.
  8. Verify that the material to be sent to the subcontractor is updated on the Material Supply Lines tab.
  9. Select the material line on the Material Supply Lines tab and click Actions > Generate Supply Order.
  10. Select the generated supply order line updated in the Supply Order Line field on the Material Supply Lines tab and click References > Supply Lines. The Warehousing Order (whinh2100m100) session is displayed.
  11. Select the outbound order line on the Outbound Lines tab and click References > Status Overview. The Outbound Line Status Overview (whinh2129m000) session is displayed.
  12. In the Outbound Line Status Overview (whinh2129m000) session, ensure that the Generate Outbound Advice and the Release Outbound Advice activities are automatically executed.
  13. On the specific menu, click Freeze/Confirm. The Shipment Lines (whinh4131m000) session is displayed.
  14. Select the shipment line and click Confirm. The shipment line Status is updated to Confirmed on the Status tab.
  15. Verify that the Line Status is Shipped for the outbound order line on the Outbound Lines tab in the Warehousing Order (whinh2100m100) session.

Previous Article Infor LN & Baan Tips & Tricks for FINANCE: Cash Flow Statements (tfgld 0123m100)
Next Article Infor LX/BPCS Tips & Tricks for EXECUTIVES:
Print
35260 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

EGLi provides Infor LX Configurable Enterprise Accounting (CEA) functionality including Advanced Transaction Processing (ATP), a configurable ledger, and batch transaction processing in the IDF architecture.

EGLi is a complete replacement for CEA. Infor LX applications integrate with EGLi, and subsystem transactions generated in Infor LX are used to create journal entries in EGLi. The Infor LX integration system parameters allow you to specify whether CEA or EGLi is your primary financial product.

We recommend that you select CEA while you test the integration. The primary financial product flag and the CEA migration programs are designed to assist existing CEA clients with their implementation of EGLi. Journals are produced in both GL systems so you can verify that the data in both GL systems are the same. This integration includes migration programs that copy your existing CEA files to corresponding EGLi files. After you run the migration programs, EGLi should be configured and ready to use. If you are already running IDF via Ming.le or SiW, before you install EGLi, you will need to see the Ming.le integration guide for instructions on how to export EGLi tasks from IDF to SiW/Ming.le.

Learn More > Infor LX Integration Guide for Enterprise General Ledger

  • Control Date Lead Times – LX provides five separate Control Date Lead Time fields so you can specify additional lead time values for Shop Orders, Purchase Orders and Planned and Firm Planned orders. Each Control Lead Time Date represents additional time (days) required at each step in the process that needs more time (Quarantine, Stabilize), that is to say, when a component is due, and when it can be used. (working with an aerospace  precision bearing manufacturer, I had to account for the QA requirement that no measurements could be taken until the parts had been “soaked” (stored) in an atmospheric controlled environment (72 degrees, and controlled humidity) for 24 hours. This requirement added one full day of lead time between each machining operation) The MPS/MRP Generation program, as well as programs that Shop Order Material Allocation records use the five control date lead times to adjust component required dates to function in the same way as the BOM Offset Lead Time.
     
  • All programs that create MRP Planned Orders, MRP Firm Planned Orders, Shop Orders, and Purchase Orders call the Control Date Calculation program (MRP515B) to establish all five control dates. A Control Lead Time Date is used to adjust the component Required Dates data in the Material Requirements file (KMR), based on planned orders for a parent, and the FMA Required Dates data, based on shop order release dates for a parent.
FirstLast

Tips: LN | Baan

Categories