Baan/LN Tip of the Week: Strategies to Issue Materials – LN

LN offers you various levels of control for the issue of materials. You can specify a different method for each material.

Available methods to control the quantity of the issue:

  • Direct user control over the quantities to issue
  • Quantities determined by the allocations

Available methods to control the time of the issue. LN issues the material:

  • After a user gives a command
  • At the allocation date
  • Immediately when the production order is released

Special methods:

  • Backflushing
  • Floor stock

Optimize Your Manufacturing Today!

Previous Article Flexfab Selects Crossroads RMC for Company Wide Implementation of Data Collection for Infor LN
Next Article BPCS/LX Tip of the Week: Role-Based Security
Print
74656 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The Credit Card Data Area program, SYS045D, enables you to create and maintain a configuration file that provides a gateway to a third-party payment application. The information you set up with this program is required to allow Infor LX to communicate with the credit card processing application that passes credit card payment information between Infor LX and the credit card providers.

Access: SYS menu

  • Use the Credit Card Data Area screen, SYS045D-01, to...

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers...