Infor LX & BPCS Manufacturing Tip: Shop Calendar Maintenance – SFC140D1

Shop calendar maintenance, SFC140D1 This program features multiple-level shop calendar maintenance. You can maintain a shop calendar at the global, facility, or work center level. Global level entries override default values found in Work Center Maintenance, CAP100D1, for any program that uses the shop calendar.

Facility overrides affect all work centers in a Facility and are exceptions to the global level. Exceptions defined at the Facility level apply to all work centers for the facility. Work Center calendar entries are the most specific. These entries apply to a single work center and override any Global or Facility conditions.

If you have deleted a work center in Work Center Maintenance, CAP100D1, you cannot delete its shop calendar. The system treats the work center shop calendar like a global calendar for that year. If you try to delete it, you will delete the global shop calendar for that year.

Range processing provides daily or weekly maintenance of all overrides for a period of up to one year with a single command.

The following explains how Infor LX uses calendars for manufactured and purchased parts planning:

  • Infor LX treats purchased and manufactured parts in the same way.
  • Infor LX does not use the work center calendar.
  • In facility planning, Infor LX uses the facility calendar.
  • If the global calendar has additional days blocked out relative to the facility calendar, MRP/MPS plans consider both the facility and global days-off.


In all cases, the system uses the item master/CIC lead time parameter to determine the release date for the planned order regarding the due date from the forecast or parent demand. The system considers days blocked out in the facility and global calendars when it determines the planned order release date.

Example: Assume the entire system (Global) has a specific date set as a regular workday. If one particular Facility recognizes this day as a holiday, no hours are available on work centers within that facility. If conditions at one work center are an exception to this holiday, that work center can be maintained with its own set of conditions.

Simulation Mode

The Shop Calendar Selection/Maintenance Simulation program, MRP747B, uses the Shop Calendar Maintenance programs, SFC140D, in a simulation mode. The MRP program allows you to maintain shop calendar information to simulate capacity planning and to view the results before you use the data in live capacity planning.

When you run MPS by facility, you cannot maintain global calendars. This safeguard prevents a user from unintentionally overwriting the live global calendar if the user runs Copy to Live, MRP770D.

Access: Menu SFC

Previous Article Infor LX & BPCS Materials Tip: Over-Receipts
Next Article Infor LN & Baan Manufacturing Tip: Performance Problems in Generate Order Planning (cprrp1210m000)
Print
13527 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

INV810 only deletes the sequence number from the ILI of the item so it is not selected again for counting and does not delete the ICY record.

The ICY Cycle Count sequential history file increases in size with each new cycle count session. Running INV015 will purge all the old ICY records up to the date entered on the set-up screen ‘Enter Cycle Count Ending Date’ field. Physically deleting the old ICY files.

In most cases, when you complete the cycle count posting and run the reports, you can reconcile the data as required. After you reconcile the data for a specific day (or group of days), you can run INV015 to purge the data for that day (or group of days).

It’s almost that time of year – AND with Crossroads RMC and Avalara, you can e-file your 1099s and other forms simply and easily!

If you plan to e-file more than 2,500 forms this year, please let us know and we’ll connect you with our Avalara representative for custom pricing. Otherwise, the link below is completely self-service. Watch the short YouTube video at the bottom of the linked page for a quick walk-through tutorial, and you’ll be ready to get started immediately!   

Learn more> Avalara 1099

123578910Last

Theme picker

Tips: LN | Baan

Are you striving to create shipping labels that cater to all your customers' needs? Do you require specific details on your shipping labels for particular items or product lines?

According to recent research, the global barcode label printer market was valued at $2.6 billion in 2022 and is estimated to reach $4.3 billion by 2032, exhibiting a CAGR of 5.2% from 2023 to 2032.

Crossroads RMC's RMClabel software automates the printing of customer-specific and item-specific labels...

Ensuring access to historical logistical and financial transaction information for your employees is crucial. However, before proceeding with archiving or deletion, it's essential to evaluate the necessity of retaining this data. Baan and Infor LN (ERP LN) offer standard archiving sessions within major modules that typically handle a significant volume of historical transactions. These sessions are designed to transfer historical data to an archive company before deleting it from the operational company.

When it comes to archiving sessions, you have three primary options:

123578910Last

Theme picker

Categories