Infor LX & BPCS Manufacturing Tip of the Week: Backward Scheduling

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers the shop calendar for weekends, shutdowns, holidays, and partial days.

Backward Scheduling Process

The algorithm starts with the due date of the shop order or planned order. The system makes the following calculations for each operation in the reverse sequence:

  1. The number of move days is subtracted from the due date (or initial date of the previous operation) to get the due date for this operation. The move days are only used on valid shop calendar days.
  2. The system uses the following calculation for the number of clock hours for the operation: Standard run or machine hrs/No. of operators + setup hours
  3. The number of clock hours is spread over the available daily capacity of the work center for those given days. The system uses the following calculation for the daily capacity of the work center: Number of shifts x hours per shift x average efficiency/100
  4. Each day is checked against the shop calendar; the calculation bypasses inactive days or adjusts for any changes in the work center capacity for that day.
  5. Queue time days are subtracted in the same manner as move time days. The resulting date is the operation start date.

The algorithm then goes to the previous operation. When all operations have been included, the resulting date is the scheduled start date of the shop order. Note that MRP uses the item lead time to determine material requirement dates on planned orders.

Previous Article It's almost the end of the 1st Quarter of 2021 -  How are you doing on your 2021 goals?
Next Article Infor LX & BPCS Tip of the Week: Credit Card Processing Within LX
Print
27772 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

This enhancement provides additional views, additional order and line details, improved navigation, and additional capabilities to the IDF Customer Order Inquiry cards and to customer order-related business objects such as Allocations, Customer Invoices, Inventory Transaction History, Promotions, Drop Shipments.

Enhanced Order views based on user roles such as customer service, warehouse/logistics, salesperson/commission, data analysis/management reporting

  • Improved sort, select and filter capabilities
  • Enhanced navigation, data organization and data display
  • Improved customer service access to all transactions throughout the entire customer order life cycle – from quote to order, related invoices, and any RMAs, return orders, related credit memos
  • Improved grouping of related fields
  • New cards to present additional order and order line details
  • Consolidation of cards and card details when appropriate
  • Enhanced Display and Maintain capabilities for drillback to related customer, ship-to, item, carrier, terms, and other master file details
  • Improved display of dates, times and applicable time zones when Region Code time zone support is implemented
  • Multi language Description, Name and Address fields displayed in user’s language, if defined, else in base language

This enhancement provides search capabilities on segment value description in Segment Value List window (WINGSVD).

Segment Value List (WINGSVD):

  • Converted to a standard subfile
  • New action code 10=Search

This makes it easier to locate segment values when defining segment values in Model Account Builder or Alias definition. In addition, WINGSVD has been redesigned as a subfile to enable WebTop grid capabilities.

FirstLast

Tips: LN | Baan

Categories