Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Kathy Barthelt

April 25th 2018 -LUNCH & LEARN WEBINAR FOR Baan & LN

NAZDAQ's B2Win Suite: Giving You Maximum Control Over Your ERP Output


Lunch & Learn Webinar for Baan & LN! 

- Giving You Maximum Control Over Your ERP Output -

NAZDAQ's B2Win Suite is the output management platform that every company needs in conjunction with its ERP system. This innovative product helps companies improve internal reporting and outbound communications.


Register today to learn how each core application is integrated into your system’s infrastructure to expand functionality, automation and improve business efficiency.

Here are a few features: 

  • Can be hosted on-premise or in cloud
  • Works with all Baan / Infor® LN versions and Mingle
  • Comes ready to work with various enterprise systems (ERP, CRM, SCM, etc.)
  • Connects with various multiple enterprise systems simultaneously (CRM, ERP, etc.)
  • Transform your ERP into different formats
  • Design completely custom formatting

 

Join us for 45 minutes: 


Watch Recorded Webinar

Previous Article Crenlo and Crossroads RMC Go International
Next Article Tip of the Week: What is Your M.O.?
Print
41597 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
FirstLast

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.