Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Anthony Etzel
/ Categories: Infor LX & BPCS Tips

BPCS/LX Tip of the Week: Purchase Order Receive All Processing LX/8.3.5

This enhancement to the Purchase Receipts screens; optionally shown with the quantity and weight fields populated with the open value on the purchase order. Previously the user had to manually enter the quantity received or, for a dynamic weight and measure items, the weight received for each line on the purchase order. Now the screens are populated with the open value and if the open value is the same as the value received, the user can simply accept the line.

The Receive All field on the PUR550D1-01 screen determines whether the receipt lines are populated with the open value. A system parameter controls the Receive All default value but the default value can be overridden. If the user specifies 1=Yes in the Receive All field then the PUR550D2-02 screen displays the open quantity or weight for each line. The user can accept the open value for each line. 

Optimize Your Manufacturing Today!

Previous Article Anthony Etzel – Featured Speaker at The New England Midrange Users Group Meeting (NEMUG) on May 16, 2018
Next Article Baan/LN Tip of the Week: Get Real!
Print
49893 Rate this article:
No rating

Contact

Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

Companies can decide to involve a subcontractor and subcontract part of their activities. The subcontractor carries out the work and returns the products to your company.

In Infor LN, subcontracting is considered as purchasing labor from a third party. Therefore, if a manufacturer wants to subcontract work, he must generate a purchase order to start the subcontracting process. These are the types of subcontracting:

  • Subcontracting with material flow
    • Operation subcontracting: For operation subcontracting, a part of the production process (one or more operations) is subcontracted.
    • Item subcontracting: For item subcontracting, an item's entire production process is subcontracted. Therefore, it is always used with material flow support.
  • Subcontracting without material flow: The simplest form of subcontracting is to generate a subcontracting purchase order to record the operations outsourced to a subcontractor. The subcontracting purchase order only represents the administrative handling of the subcontracting process. When the subcontracted item is received back from the subcontractor, you must close the subcontracting purchase order, which initiates the production process.
  • Unplanned subcontracting: Unplanned subcontracting is applicable when you subcontract after generating a production order. For unplanned subcontracting, a purchase order is generated from the production order and the material supply lines are populated by Shop Floor Control.
  • Service subcontracting: For service subcontracting, work on an item to be maintained or repaired is subcontracted. This work entails the entire repair process, or only a part of it. Service subcontracting can be used with or without material flow support.

To start the subcontracting process, a purchase order is required.