BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Previous Article Baan/LN Tip of the Week: Data Sizing Moving to LN
Next Article Filtec Selects Crossroads RMC for Baan Data Collection
Print
63080 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Enhances purchase order efficiency by automatically calculating the Vendor Delivery Date based on user input.

  • When a purchase order line is created, the user enters the item, order quantity, and Due Date.

  • LX automatically calculates the Vendor Delivery Date, adding buffer time for quality control, testing, and inspection activities.

  • If the Due Date is revised, an informational message prompts the user to review and potentially update the Vendor Delivery Date.

Enhancements:

  • A new PUR820 system parameter enables automatic recalculation of the Vendor Delivery Date.

  • Instead of a manual reminder, PUR500 now issues a message: “Vendor Delivery Date recalculated,” showing the updated date.

Benefits:

  • Eliminates the need to manually review and update the Vendor Delivery Date.

  • Removes the need to delete and recreate PO lines to trigger automatic date calculation.

Enables integration between LX and Infor OS Federation Services (IFS) to automate user provisioning.

  • Bi-directional user synchronization between Infor OS and LX:

    • Infor OS user creation or changes automatically create or update users in LX.

    • IBM i user profiles can be created if needed.

    • Updates to SYS600 user data are reflected in Infor OS.

  • Security Role Integration:

    • LX Security Roles and Units are published as IFS Security Roles via SyncSecurityRoleMaster BODs.

    • LX receives inbound SyncSecurityUserMaster BODs from IFS to create or update user records in SYS600.

    • SYS600 Exit Points trigger ProcessSecurityUserMaster BODs to request user creation or updates in IFS on behalf of LX.

Available Versions: 8.3.5, 8.4.1, 8.4.2