Infor LX/BPCS Tips & Tricks for OPERATIONS: Multi-Level Shop Order Release Due Dates

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

Previous Article Infor LX/BPCS Tips & Tricks for FINANCE: Override Exchange Rate
Next Article Infor LX/BPCS -Join Us for an Exclusive Insight into Data Collection Streamlining
Print
12206 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Enhances purchase order efficiency by automatically calculating the Vendor Delivery Date based on user input.

  • When a purchase order line is created, the user enters the item, order quantity, and Due Date.

  • LX automatically calculates the Vendor Delivery Date, adding buffer time for quality control, testing, and inspection activities.

  • If the Due Date is revised, an informational message prompts the user to review and potentially update the Vendor Delivery Date.

Enhancements:

  • A new PUR820 system parameter enables automatic recalculation of the Vendor Delivery Date.

  • Instead of a manual reminder, PUR500 now issues a message: “Vendor Delivery Date recalculated,” showing the updated date.

Benefits:

  • Eliminates the need to manually review and update the Vendor Delivery Date.

  • Removes the need to delete and recreate PO lines to trigger automatic date calculation.

Enables integration between LX and Infor OS Federation Services (IFS) to automate user provisioning.

  • Bi-directional user synchronization between Infor OS and LX:

    • Infor OS user creation or changes automatically create or update users in LX.

    • IBM i user profiles can be created if needed.

    • Updates to SYS600 user data are reflected in Infor OS.

  • Security Role Integration:

    • LX Security Roles and Units are published as IFS Security Roles via SyncSecurityRoleMaster BODs.

    • LX receives inbound SyncSecurityUserMaster BODs from IFS to create or update user records in SYS600.

    • SYS600 Exit Points trigger ProcessSecurityUserMaster BODs to request user creation or updates in IFS on behalf of LX.

Available Versions: 8.3.5, 8.4.1, 8.4.2