Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: 15 Reconciliation Steps for GRNI Transactions

How many are you missing in your process?

The reconciliation process of the Goods Received Not Invoiced (GRNI) transactions consists of the following steps:

  1. Close the financial period so that no new transactions can be entered.
  2. Print the trial balance.
  3. Print a report of the invoices to be received.
  4. Compare the reports.
  5. Print the reconciliation data.
  6. Examine the reports.
  7. Rebuild the History.
  8. Print the trial balance and the reconciliation report again.
  9. Print the GRNI reconciliation checklist.
  10. Check the balances on the GRNI reconciliation checklist.
  11. Analyze the reconciliation data.
  12. Make corrections.
  13. Print the GRNI reconciliation checklist again.
  14. Post the reconciliation correction transactions.
  15. Accept the reconciliation data.
Previous Article Optimize with Infor Development Framework: IDF
Next Article Is Your ERP System Hurting Your Business?
Print
56120 Rate this article:
3.3
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Enhances purchase order efficiency by automatically calculating the Vendor Delivery Date based on user input.

  • When a purchase order line is created, the user enters the item, order quantity, and Due Date.

  • LX automatically calculates the Vendor Delivery Date, adding buffer time for quality control, testing, and inspection activities.

  • If the Due Date is revised, an informational message prompts the user to review and potentially update the Vendor Delivery Date.

Enhancements:

  • A new PUR820 system parameter enables automatic recalculation of the Vendor Delivery Date.

  • Instead of a manual reminder, PUR500 now issues a message: “Vendor Delivery Date recalculated,” showing the updated date.

Benefits:

  • Eliminates the need to manually review and update the Vendor Delivery Date.

  • Removes the need to delete and recreate PO lines to trigger automatic date calculation.

Enables integration between LX and Infor OS Federation Services (IFS) to automate user provisioning.

  • Bi-directional user synchronization between Infor OS and LX:

    • Infor OS user creation or changes automatically create or update users in LX.

    • IBM i user profiles can be created if needed.

    • Updates to SYS600 user data are reflected in Infor OS.

  • Security Role Integration:

    • LX Security Roles and Units are published as IFS Security Roles via SyncSecurityRoleMaster BODs.

    • LX receives inbound SyncSecurityUserMaster BODs from IFS to create or update user records in SYS600.

    • SYS600 Exit Points trigger ProcessSecurityUserMaster BODs to request user creation or updates in IFS on behalf of LX.

Available Versions: 8.3.5, 8.4.1, 8.4.2

FirstLast

Tips: LN | Baan

Categories