Infor LX & BPCS Manufacturing Tip of the Week: Backward Scheduling

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers the shop calendar for weekends, shutdowns, holidays, and partial days.

Backward Scheduling Process

The algorithm starts with the due date of the shop order or planned order. The system makes the following calculations for each operation in the reverse sequence:

  1. The number of move days is subtracted from the due date (or initial date of the previous operation) to get the due date for this operation. The move days are only used on valid shop calendar days.
  2. The system uses the following calculation for the number of clock hours for the operation: Standard run or machine hrs/No. of operators + setup hours
  3. The number of clock hours is spread over the available daily capacity of the work center for those given days. The system uses the following calculation for the daily capacity of the work center: Number of shifts x hours per shift x average efficiency/100
  4. Each day is checked against the shop calendar; the calculation bypasses inactive days or adjusts for any changes in the work center capacity for that day.
  5. Queue time days are subtracted in the same manner as move time days. The resulting date is the operation start date.

The algorithm then goes to the previous operation. When all operations have been included, the resulting date is the scheduled start date of the shop order. Note that MRP uses the item lead time to determine material requirement dates on planned orders.

Previous Article It's almost the end of the 1st Quarter of 2021 -  How are you doing on your 2021 goals?
Next Article Infor LX & BPCS Tip of the Week: Credit Card Processing Within LX
Print
33043 Rate this article:
5.0

Contact

George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

FirstLast

Tips: LN | Baan

Industry Insight: Why ERP Data Stays Siloed, and What to Do About It

Most manufacturers don't have a data problem. They have a connection problem.

Production data lives in one system. Sales and customer data lives in another. Finance runs somewhere else entirely. Each system does its job well on its own, but without a way to connect them, the organization never gets the full picture, and neither do the people trying to run the business.

Why This Happens
ERP systems are often the core of a manufacturer's operations, but they rarely operate alone. Over time, businesses add third-party software for CRM, e-commerce, warehouse management, EDI, and more. Each addition solves an immediate need, but without integration, it also creates another silo.

The result is familiar across manufacturing: teams end up manually re-entering data between systems, waiting on reports that should be immediate, and making decisions without visibility into what's happening elsewhere in the business.

Integration vs. Enhancement
There are two ways to close this gap, and they solve different problems:

  1. ERP Integration connects your ERP to the third-party software you use every day, creating a single source of data instead of several disconnected ones. Whether it's a one-way, two-way, or complex systems integration, the goal is the same: eliminate errors, reduce manual entry, and give everyone access to the same real-time information.
  2. ERP Enhancement goes a step further, creating new functionality or modifying existing functionality within the ERP itself, so the system matches how your business actually operates rather than forcing your business to adapt to the system's limitations. Done right, enhancements use parameter-co

Categories