Infor LN & Baan Tips & Tricks for OPERATIONS: Absorbing Cost Items into Projects

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items:

    • If needed, create the cost items.
    • Create a purchase order for the cost items without referencing a project number.
  4. Matching PO to Costs:

    • When matching the purchase orders in session tfacp2107m000, select "Add Costs" from the specific menu on the toolbar (you'll need to be in the matching details to access this).
    • This will open session tfacp1133s000, where you will enter the previously specified ledger account number.
    • Once done, the "PCS Transactions" option on the toolbar becomes available. Selecting this brings up session tipcs3140m000 (General Actual Project Costs).
       
  5. Disbursing Costs to Projects: In session tipcs3140m000, the PO costs for the cost items can be disbursed to any open and active project.

Since these are cost items, they won't go into stock. The key is ensuring that the cost disbursement ("Add Costs") is correctly linked to the appropriate project, giving users visibility of the cost items as general project costs.
 

Previous Article Infor LN & Baan Tips & Tricks for EXECUTIVES
Next Article Infor LN & Baan Tips & Tricks for TECHNOLOGY: Adding a Timestamp to LN Standard Tables
Print
24096 Rate this article:
5.0

Contact

Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Tips: LN | Baan

Note: The Blocked Operations (tisfc0540m000) session displays the blocked operations.

Introduction

Sometimes a problem occurs that must be solved before an operation proceeds. Examples of such situations are:

  • The quality of an intermediate product must first be inspected.
  • A machine is in repair.
  • A supplier cannot deliver an essential component in time.
  • A customer is late with its payments.

In these situations the operation can get the operation status Blocked.

An operation can be blocked:

  • Manually.
  • Automatically by Quality.

Blocking reasons

Every blocked operation must have a blocking reason. The blocking reason of a blocked operation has two purposes:

  • To indicate why the operation is blocked.
  • To determine which actions you can no longer perform on the operation.

Types of blocking

The following actions can be blocked by means of a blocking reason:

  • Reporting a quantity completed.
  • Reporting a quantity rejected.
  • Reporting a quantity to be inspected.
  • Reporting an operation completed.

You normally carry out these actions in the Report Operations Completed (tisfc0130m000) session.

You can define blocking reasons in the Blocking Reasons (tisfc2100m000) session.

Manual blocking

Use the Report Operations Completed (tisfc0130m000) session to block an operation. When you block an operation, you must also enter a blocking reason. If Quality has already blocked the operation, you can only enter a blocking reason, which is more restrictive than the blocking reason of Quality.