Baan/LN Tip of the Week: Safety Time


You can add safety time in the item master for the item. This will add the number of days safety time to the order lead time thus bringing the order in x number of days early. (x is the safety time).

The safety time is on form 4 of the item master in Baan IV and in Item Ordering Data – Generation I tab in Baan V and LN.

Previous Article BPCS/LX Tip of the Week: How does ERP LX establish costing for purchased items?
Next Article BPCS/LX Tip of the Week: Batch Allocation
Print
99412 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

How can I use an alternate item on a shop order?

The best way is to have the approved alternate item appear on the Bill of Material just after the standard item with a zero required quantity. Now the alternate item will appear on the Shop Order. So, if the standard item is not available, the alternate item can be issued to the shop order.

When the shop order is closed out, one item will have an unfavorable variance while the other shows a favorable variance. This is an easy way to provide alternate items provided engineering approves and they are part of the Bill of Material.

FirstLast

Tips: LN | Baan

Categories