BPCS/LX Tip of the Week: What is the bubble number and how do I maintain it?

The bubble number is maintained at the component level for each component defined on the Bill of Material. It is an extra user-defined reference number that you can use to re-sequence the maintenance screen display or bills of material listings.

In Infor LX, the system displays the bubble number for the existing child items. Engineering drawings often use a bubble number at the component level on the drawing so that same bubble number can be used on the Bill of Material for a link of the component to the drawing. Alternatively, you may use it simply as a method to sequence the BOM.

Be careful of how you assign the number. It is a good idea to assign the number with a consecutive count by 10 leaving room to allow for component additions to the Bill of Material.

Previous Article Baan/LN Tip of the Week: Setting Up New Employees in LN
Next Article Crossroads RMC to Exhibit at Manufacturing Matchmaking 2014
Print
79397 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

If you setup the “From” and “To” Location fields in the Work Center file, this will determine the locations for material issue transactions and production reporting transactions.

The reporting of the transactions happen through production reporting, JIT600, or using the Shop Floor labor posting, SFC600, or Shop Floor Posting from SFC650.

Remember, any location used in the work center file must first be set up in the location master file. Using an MES solution by-passes the need to key any of the data to Infor LX.

Ok… so you want to know the status of a specific shop order that was released two days ago.

What do you do?

It’s a sure bet that you have a manager, supervisor, or planner who can walk the floor and find the order at whatever work center it happens to be at. He/she can then answer “what operations have been completed and how many were completed?” All this requires leg work, and of course, a fair amount of time.

Now, if you have set up your BPCS master files properly, and you report transaction activity, you should be able to get those shop order statuses much faster using the SFC300 Shop Order Inquiry Screen.

At your fingertips you can see:

  • Release date & due date
  • How many hours remain in total and at each operation
  • The quantity required, what was finished, and the remaining quantity
  • What components (materials) have been issued

Pretty basic information, right? Are you getting what you need to know? If not, then you may want to reexamine how your BPCS files are set up and what transactions along with their frequency are captured.

FirstLast

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.