BPCS/LX Tip of the Week: Product Routing

Defining the Product Routing first requires the items to be setup in the Item Master file. Other master files also need to be defined prior to creating the routing.
These include:

  • The Facility defined with a SYS program
  • The Warehouses defined with an INV program
  • Locations defined with an INV program
  • The Machines (required if using capacity planning or an MES interface) defined with an MDM program

After the above data is set up, the Department file and Work Center files can be setup in MDM. Now you are ready to define a product route.

Previous Article Baan/LN Tip of the Week: Month End – Miscellaneous To-Do’s
Next Article Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance
Print
68099 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

You can change your master schedule by specifying the type of master schedule update to perform. You can run a Net Change or Regenerative Schedule.

You also have the ability to clear the lower level requirements out of the Planned and Firm-Planned Order file.

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.